WEST TEXAS TRANSMISSION PLANNING Workshop for Public Utility Commission Project No. 25819 07242002 - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

WEST TEXAS TRANSMISSION PLANNING Workshop for Public Utility Commission Project No. 25819 07242002

Description:

STATCOM/DVAR/Mini SVC Devices. Accurate & Appropriate Aggregated Models Needed. 07/24/2002 ... MODEL DEVELOPMENT. Development and Validation ERCOT Wind ... – PowerPoint PPT presentation

Number of Views:2429
Avg rating:3.0/5.0
Slides: 16
Provided by: kennetha3
Category:

less

Transcript and Presenter's Notes

Title: WEST TEXAS TRANSMISSION PLANNING Workshop for Public Utility Commission Project No. 25819 07242002


1
WEST TEXAS TRANSMISSION PLANNINGWorkshop for
Public Utility CommissionProject No. 25819
07/24/2002
  • KENNETH A. DONOHOO, P.E.
  • Manager of System Planning, Technical Operations
  • kdonohoo_at_ercot.com
  • www.ercot.com

2
TRANSMISSION SYSTEM
  • Is a Network
  • Not a one way system
  • Flows change with changing system conditions
  • Events on the network can have far reaching
    effects across the whole system
  • All customers share the benefits of a reliable
    interconnected network
  • Is constantly changing and is very rapid
  • Generation Output Changes
  • Transmission System Changes

3
MAJOR CONCERNS
  • HOW MUCH PEAK CAPACITY SHOULD ERCOT BUILD
    TRANSMISSION FOR?
  • Seasonal Production
  • Diversity
  • Time of Day
  • Generation Interconnect Agreements
  • STABILITY AFFECTS
  • As the Wind Blows
  • Regulation Ancillary Services
  • Accurate Appropriate Aggregated Models Needed
  • VOLTAGE CONTROL
  • As the Wind Blows
  • May Be Critical for Keeping Renewable Online
  • High Voltage Off Peak a Major Concern
  • STATCOM/DVAR/Mini SVC Devices
  • Accurate Appropriate Aggregated Models Needed

4
WEST TEXAS CURRENT
  • TRANSMISSION TRANSFER LIMIT
  • 1,100 MW to 1,300 MW
  • Stability Thermal Limits
  • EXISTING GENERATION
  • 5,000 MW
  • Growing Everyday
  • LOAD
  • 3,300 MW
  • 1.0 to 1.5 Per Year Growth
  • EXPORTABLE GENERATION
  • 1,700 MW
  • Higher Under Light Load Conditions

5
WEST TEXAS POSSIBLE FUTURE
  • GENERATION
  • 7,000 MW to 8,500 MW
  • LOAD
  • 3,300 MW
  • EXPORTABLE GENERATION
  • 3,700 MW to 5,200 MW
  • 100 to 200 INCREASE
  • TRANSFER LIMIT 1,800 MW to 2,300 MW
  • Stability Thermal Limits
  • Voltage Limits

6
WEST TEXAS TRANSFER STUDY
7
Alternative A
  • 345 kV Morgan Creek San Angelo Comanche SW
    Comanche Peak circuit
  • 345 kV Jacksboro West Denton circuit
  • 24 other transmission upgrades
  • 1,827 Mvar of capacitor banks
  • 270M cost index

8
Alternative B
  • 345 kV San Angelo Killeen circuit
  • 345 kV Jacksboro West Denton circuit
  • 18 other transmission upgrades
  • 1,838 Mvar of capacitor banks
  • 337M cost index

9
Alternative C
  • 345 kV Morgan Creek Parker circuit
  • 345 kV Jacksboro West Denton circuit
  • 18 other transmission upgrades
  • 1,226 Mvar of capacitor banks
  • 356M cost index

10
Alternative D
  • 765 kV Morgan Creek West Denton circuit
  • 345 kV West Denton NW Carrollton circuit
  • 345 kV West Denton Anna circuit
  • 11 other transmission upgrades
  • 978 Mvar of capacitor banks
  • 480M cost index

11
Alternative E
  • DC Line Odessa West Denton circuit
  • 345 kV West Denton NW Carrollton circuit
  • 345 kV West Denton Anna circuit

12
Preliminary Results
  • Studies have been performed for options A C and
    both alternatives indicated to be unstable (not
    acceptable)
  • Both cases are unstable in steady state without
    static VAR devices located at wind generation
    sites
  • Suspect options B D will also be unstable
  • VAR devices may be critical to keeping system
    stable and wind generation on line
  • Propose change in Reactive Standards for Wind
    Generation
  • Dynamic modeling of the wind farms and the
    combined cycle plants are problematic in
    completing this work

13
MODEL DEVELOPMENT
  • Development and Validation ERCOT Wind Generation
    Models
  • Contract Complete and Executed 07/22/2002
  • Electrotek Concepts, Inc.
  • ERCOT System Planning Staff is Leading the
    Project
  • Provides significant support to Wind Generation
    projects
  • Includes monitoring of four sites

14
PROJECT TIMELINE
15
QUESTIONS
Write a Comment
User Comments (0)
About PowerShow.com