Title: C-5 Corrosion Prevention Compound (CPC) Application/Evaluation Program
1C-5 Corrosion Prevention Compound (CPC)
Application/Evaluation Program
U.S. Air Force Presentation
March 2006
- Dan McTish / Scott Jones
- Lockheed Martin Aeronautics Company
- 770-494-4489
- dan.j.mctish_at_lmco.com
- scott.a.jones_at_lmco.com
2Introduction
- This work is being performed under an OSD
initiative to fund corrosion prevention and
control projects that would provide rapid,
measurable, corrosion benefit to weapon systems. - WR-ALC received matching funds for conducting a
field trial of proven corrosion prevention
compounds (CPC) on operational aircraft. - WR-ALC Program Manager
- Mr. Buc McRory
- DSN 468-6663
- Comm 478-926-6663
3C-5 CPC Team
- Team composed of technical experts from all
associated fields. - WR-ALC (Buc McRory)
- Battelle (Bill Abbott, Ernie Patterson)
- USAF Corrosion Office (Dick Kinzie)
- ANG Corrosion Office (Jerry Powell)
- HQ/AFRC (Mark McIntosh)
- 439 AW / Westover ARB (MSgt Robert Ivey)
- 433 AW / Lackland AFB (MSgt Nick Peche)
- 105AW / Stewart ANG (MSgt Larry Keeno, TSgt Stan
Hyla) - 445AW / Wright Patterson AFB (TSgt Scott McCoy)
- SKT (Jill Ullett, Charlie Gibbs)
- USAFA (LtCol Scott Fawaz)
- University of Virginia (Rob Kelly)
4C-5 Fleet
5Contract
- CPCs Were Applied To Corrosion-Prone Areas On 6
C-5A Aircraft In May 2005. - CPCs Were Not Applied Over Corrosion.
- Aircraft Were Provided From Westover ARB, Stewart
ANG and Lackland AFB. - CPC Performance Being Monitored For A Period Of
24 Months (February 2007). - Copper sensors (unobtrusive) from Battelle were
installed in all areas. - Steel sensors (short life) were only installed in
wet areas. - Coated and Uncoated Sensors were installed in
each area. - Sensor Data Downloads and Visual Inspections
being performed at 120 day intervals. - Data to be used to determine
- Effectiveness
- Dirt Accumulation
- Reapplication Intervals
- CPC Touch-up No Longer Being Performed. Need to
Determine Service Life.
6CPC SELECTIONTypes of CPC
- Thin Film (D-5026NS, AV-25, LPS2)
- Displace water and penetrate voids in faying
surfaces, cracks, and around fastener heads. - Less effective in areas of high water runoff when
compared to waxy or hard film compounds. - Waxy (Not Used)
- Non-water displacing or barrier type compounds.
- Do not penetrate faying surfaces very well.
- Dirt accumulation a problem.
- Hard Film (Cor-Ban35, AV-15, Procyon)
- Penetrating, water-displacement capabilities
along with barrier type performance with one
product. - Penetrate voids, cracks, or faying surfaces and
displace moisture. - Cures to a very firm, non-tacky, barrier type
film.
7CPC SELECTIONConsiderations
- All CPC are considered temporary when compared to
the more durable paint type finishes like epoxy
primer and polyurethane topcoats. - Periodic reapplication and/or touch-up will be
required for CPC to remain effective. - Visual inspections will be primary CPC evaluation
method. - Sensor Data will be used to evaluate CPCs and to
determine if reapplications are beneficial. - Up to 64 Sensors Installed on Each C-5 Aircraft.
- Reapplication intervals expected to be anywhere
from 1 year to several years. - CPCs can be utilized on C-5 aircraft as an
inexpensive approach (over paint) to provide
additional corrosion protection in bilge and
empennage.
8CPC SELECTIONDecision Process
- Data used to select CPC for each treatment area
- Corrosion Type
- SCC, exfoliation, paint degradation, fluid
entrapment, condensation, or a combination - Environmental Influences
- 120 Day Wash Cycle in wheel well, chine, tiedown
pans - Existing fluids in faying surfaces - bilge
- Excessive Heat on Upper Lobe Skins (160F)
- Reapplication Requirements
- Material (ferrous/non-ferrous)
- Existing Finish
9C-5 CPC TREATMENT AREASSELECTION PROCESS
- Data used to select corrosion prone areas
- User Conferences (CPAB, ASIP, FSIP, PIWG)
- Corrosion Manual (T.O. 1C-5A-23)
- Discrepancy Forms (AFTO 107, AFTO 202, AFTO 95)
- Discrepancy Databases (FODATS, STFS)
- Open Communication (Telecom, Email)
- Candidate treatment areas were finalized based
upon the following requirements - Accessibility (Base level)
- Varying environmental conditions
- Data applicable to multiple areas
10(No Transcript)
11NLG Wheel Well Aft Bulkhead (FS 664) LHS
OnlyCor-Ban 35, AV-15, Procyon
12NLG Wheel Well Aft Bulkhead (FS 664) LHS
OnlyCor-Ban 35, AV-15, Procyon
69-0027
Nicks From NLG Wheel Spin Debris Aerosol Touch-up
13MLG Mainframes (FS1303/1383/1523/1603) LHS
OnlyCor-Ban 35, AV-15, Procyon
14MLG Aft Bulkhead (FS1638) LHS OnlyCor-Ban 35,
AV-15, Procyon
15MLG Aft Bulkhead (FS1638) LHS OnlyCor-Ban 35,
AV-15, Procyon
16Keel Beam Vertical Panel LHS OnlyCor-Ban 35,
AV-15, Procyon
17Keel Beam Horizontal Shelf LHS OnlyCor-Ban 35,
AV-15, Procyon
18Keel Beam Horizontal Shelf Steel
SensorsCor-Ban 35, AV-15, Procyon
After 150 days on 68-0212
19Forward Ramp Cargo Tiedown ReceptaclesCor-Ban
35, AV-15
20Forward Ramp Cargo Tiedown ReceptaclesCor-Ban
35, AV-15
21Chine Cove from FS1884 thru FS1964 RHS
OnlyCor-Ban 35, AV-15, Procyon
22Floor Panel Behind Troop Latrine RHS
OnlyCor-Ban 35, AV-15, Procyon
23Fuselage Belly Skins from FS1064 to FS1106 RHS
OnlyD-5026NS, AV-25, LPS-2
24Bulkhead End Fittings at FS1064 FS1106 RHS
OnlyD-5026NS, AV-25, LPS-2
25Intermediate End Fittings at FS1084 FS1128
RHS OnlyD-5026NS, AV-25, LPS-2
26Crew Lavatory Ground Service Pan - RHS
OnlyCor-Ban 35, AV-15, Procyon
27Crew Lavatory Ground Service Pan - RHS
OnlyCor-Ban 35, AV-15, Procyon
28Crew Lavatory Ground Service Pan - RHS
OnlyD-5026NS, AV-25, LPS-2
29Crew Lavatory Ground Service Pan - RHS
OnlyD-5026NS, AV-25, LPS-2
30Pressurized Upper Lobe Skin, Frames Stringers
D-5026NS, AV-25, LPS-2
31UnPressurized Upper Lobe Skin, Frames
Stringers D-5026NS, AV-25, LPS-2
32UnPressurized Upper Lobe Skin, Frames
Stringers D-5026NS, AV-25, LPS-2
33C-5 CPC TREATMENT AREASCPC Selection
34Total Flight Hours (Cumulative)
35Sensor Data 120 days
36Program Status Hard Film CPC
- Hard films applied using both HVLP equipment and
aerosol cans. - Hard film CPC (CorBan35, AV-15) performing well,
with only minor touch-ups to nicks behind gear.
(Touch-ups no longer being performed) - Procyon not surviving operational environment.
- Dyed (salmon, brown) hard film use over white
paint in wheel wells resulted in negative
feedback. White wheel wells easier to keep
clean. - Undyed CorBan 35 and Undyed AV-15 applied with
much better feedback from base personnel. - CorBan 35 and AV-15 application results over
cadmium depleted fasteners in cargo tiedown pans
still inconclusive. (UV issues)
37CorBan 35 Dyed vs. Undyed
38AV 15 Dyed vs. Undyed
39Program Status Thin/Oily Film CPC
- Thin films applied using aerosol cans.
- Confined bilge area applications attempted with
HVLP equipment, but aerosol cans provided much
better mobility. - Bio-Environmental tested air during aerosol bilge
applications. Full face respirators were
recommended but half-face were sufficient. - Thin oily films in upper lobe providing
protection, but excessive heat (160F) is causing
some CPCs to evaporate after only 120 days on
exposed surfaces. Benefits may still be realized
over time. - Reapplications performed in upper lobe at 120
days on 3 aircraft to determine if reoccurring
applications are necessary. - Thin oily films in bilge remaining oily to touch
after 8 months and three wash cycles. - Minimal dirt accumulation in bilge after 8
months.
40Thin/Oily Film CPC Dirt Accumulation
After 8 Months on Flight Line Fence
41Current Program Issues
- Coat additional areas with thin film CPCs on
bilge skins and upper lobe skins to obtain more
performance data. - Determine from sensor readings and visual
inspections if continual reapplications of thin
film CPCs in HOT upper lobe are necessary. - Continue to monitor thin film CPCs for dirt
accumulation. - Verify Undyed hard film CPC is preferred over
white paint in wheel wells. - Determine if CPC products will be listed by
product name or by specification in tech orders. - Ground test CorBan 22 self-healing soft film for
possible use on Horizontal Pivot Shafts. - Propose that CPCs and sensors not be removed
from aircraft in February 2007 and that bi-annual
performance evaluations be performed.
42C-5 CPC Application/Evaluation Field Team
43CLOSING REMARKS / ADJOURN