Title: North West provincial Treasury presentation on Conditional Grants and Capital Expenditure as at 30 J
1North West provincial Treasurypresentation on
Conditional Grants and Capital Expenditure as at
30 June 2008
2Introduction
- The report on the performance of conditional
grants and capital expenditure covers the period
1st April 2008 to the 31st June 2008 - Expenditure for this period under review is based
on the straight line assumption of 25.
3Provincial Summary
- The provincial main budget for 2008/09 is
R16,937 billion. - Spending for the 1st quarter amounts to R3,811
billion or 22,5. - The conditional grant budget for the 2008/09
financial year is R2,5 billion . - Expenditure on the conditional grants for the 1st
Quarter amounts to equals R429,8millon or 17. - Amounts transferred in terms of the DORA is R746
million, the province spent R429,8 million which
equals 58 expenditure.
4(No Transcript)
5Provincial Summary Conditional Grants
6Provincial Summary Infrastructure Funds
- The infrastructure budget equals R2.5 billion for
the 2008/09 financial year. - Expenditure on the Infrastructure funds equals
17 of approved budget which is 8 short on the
estimated 25.
7NW Office of the Premier Infrastructure Funds
- The Office of the Premier has spent 36 of their
approved budget. - Spending is progressing well with the unspent
funds already committed to complete the
maintenance and construction of traditional
council offices. - Project will be completed by the 31 July 2008.
8Conditional Grants/Infrastructure Exp.
9NW Department of Health
- CONDITIONAL GRANTS SPENDING
- Average spending of 17 on conditional grant has
been registered under Health - Hospital Revite Slow progress in Hospital that
should have been completed namely Moses Kontane,
Vryburg Hospital. - Professional training and development
Reclassification of business plan delayed
implementation process. - HIV/AIDS Late transfer of funds from National
and late submission of business plans from NGOs
delayed spending. - Forensic Pathology The unspent funds are
reserved for the building of mortuary at
Kerksdorp/Tshepong Hospital.
10NW Department of Health
- Receipt of maintenance plans late from DPW
subsequent the reprioritization processes - Inconvenient procurement process- delayed payment
processes. - Delays in finalising sites for clinics
- Cancellation of contracts due to non performance
of contractors.
11NW Department of Sport, Arts and Culture
12NW Department of Sport, Arts and Culture
- The Community Library Services Grant spent a mere
6 as a result of the late planning, tendering
procedures, staff recruitment and training. - Spending on the Mass sport and recreation Grant
seems problematic. The funds has apparently been
divided between the departments new regional
offices and no spending is taking place. - The spending on the archive building projects is
significantly going well at 76.01 . - Department of Public Works is addressing the
matter of Khuma library site that belonged to
Health to allow spending on libraries.
13NW Economic Development and Tourism
- The none spending on MIDZ is as a result of the
land issue for erecting MIDZ infrastructure. - The operating permit not yet approved by the
Department of Trade and Industry (DTI) .
14NW Department of Education
15NW Department of Education
-
- Low spending due to late delivery of HIV/AIDS
material, spending has since improved. - Infrastructure grant delay in finalisation of
budgets, reprioritisation of projects and plans,
contractors are now on site. - Delays in finalisation of plans for sanitation
and fencing of schools, projects are at tender
stage. - Nine (9) projects for minor and major renovations
have now started, the projects will be completed
in 3 months time.
16NW Department of Local Government and Housing
17NW Department of Local Government and Housing
- Low spending on Integrated Housing were as a
result of the delay in registering contractors
with NHBRC and this impacted negatively on the
implementation and delivery of projects. - The zero expenditure on the Bucket replacement
was due to the lack of readiness by
Municipalities in terms of capacity.
Municipalities has to first erect the structures
and claim the funds from the department. - With regard to Disaster Management
Municipalities were not readily available with
the business plans and as a result no transfer
payments could be made.
18NW Department of Transport, Roads and Community
Safety
19NW Department of Transport, Roads and Community
Safety
- The low spending pattern on the infrastructure is
due to reprioritization of projects and delays in
the tendering processes. - Low spending on the EPWP and maintenance projects
is due to transformation of the implementation
of EPWP processes, hence project delivery was
delayed.
20NW Department of Public Works
21NW Department of Public Works
-
- Devolution of Property rates Taxes The 1st
transfer from National will be effected only in
August 2008, the total budget is R58 million. - Monitoring and evaluation on projects are being
fast tracked due to implementation of IDIP
delivery processes. - Slow spending on maintenance has been registered
as a result of lack of capacity and poor
communication between client departments and the
agent. As a remedial measure, the IDIP focus will
now be on maintenance.
22NW Department of Social Development
23NW Department of Social Development
- Secure care centres under spending is due to the
delay in finalizing the construction of the wall
and the special fencing. - Substance abuse centre The purchase of a
building for the substance abuse centre for
in-patients will be completed in November 2008
and renovations will be completed within three
months thereafter.
24NW Department of Agriculture, Conservation and
Environment
25NW Department of Agriculture, Conservation and
Environment
- The Department has spent 5 due to lack of the
necessary capacity to design specifications and
implement projects. - The tender for the outsourcing of the design of
specifications and appointment of Engineers will
be finalised in Septemeber 2008 - The outsourcing the service will address the
spending on Land Care Comprehensive
Agricultural Support and Settlement Support.
26Concluding Remarks
- Although the total spending by the province seems
to be fair, special attention has to be paid in
addressing the spending on conditional grants and
infrastructure. - At this point in time the province does not have
any surplus funds to assist departments with
budget pressures . - Provincial Treasury has set special meetings with
MECs and Heads of Departments of the affected
departments to address the issues of under
spending of allocated budgets. - Monthly presentation and discussion of
expenditure reports at Heads of Department
meetings empowers departments to addressing the
gaps that attributes to under spending. -
27Concluding Remarks
- The rollout of the Infrastructure Delivery
Improvement Programme (IDIP) within the province
and the active involvement of the Provincial
Treasury with the Provincial Departments of
Education, Public Works and Health and the
National Treasury definitely revealed positive
results in the infrastructure planning, delivery
and management. - The NW provincial treasury continues to meet
provincial departments regularly to facilitate
the acquiring of resources, requisite skills to
improve budget planning and spending capacity and
to address areas where there are risks of both
over and under spending.
THANK YOU