Description:

The spending on the archive building projects is significantly going well at 76.01 ... on MIDZ is as a result of the land issue for erecting MIDZ infrastructure. ... – PowerPoint PPT presentation

Number of Views:41
Avg rating:3.0/5.0
Slides: 28
Provided by: frankab
Category:

less

Transcript and Presenter's Notes

Title: North West provincial Treasury presentation on Conditional Grants and Capital Expenditure as at 30 J


1
North West provincial Treasurypresentation on
Conditional Grants and Capital Expenditure as at
30 June 2008
2
Introduction
  • The report on the performance of conditional
    grants and capital expenditure covers the period
    1st April 2008 to the 31st June 2008
  • Expenditure for this period under review is based
    on the straight line assumption of 25.

3
Provincial Summary
  • The provincial main budget for 2008/09 is
    R16,937 billion.
  • Spending for the 1st quarter amounts to R3,811
    billion or 22,5.
  • The conditional grant budget for the 2008/09
    financial year is R2,5 billion .
  • Expenditure on the conditional grants for the 1st
    Quarter amounts to equals R429,8millon or 17.
  • Amounts transferred in terms of the DORA is R746
    million, the province spent R429,8 million which
    equals 58 expenditure.

4
(No Transcript)
5
Provincial Summary Conditional Grants
6
Provincial Summary Infrastructure Funds
  • The infrastructure budget equals R2.5 billion for
    the 2008/09 financial year.
  • Expenditure on the Infrastructure funds equals
    17 of approved budget which is 8 short on the
    estimated 25.

7
NW Office of the Premier Infrastructure Funds
  • The Office of the Premier has spent 36 of their
    approved budget.
  • Spending is progressing well with the unspent
    funds already committed to complete the
    maintenance and construction of traditional
    council offices.
  • Project will be completed by the 31 July 2008.

8
Conditional Grants/Infrastructure Exp.
9
NW Department of Health
  • CONDITIONAL GRANTS SPENDING
  • Average spending of 17 on conditional grant has
    been registered under Health
  • Hospital Revite Slow progress in Hospital that
    should have been completed namely Moses Kontane,
    Vryburg Hospital.
  • Professional training and development
    Reclassification of business plan delayed
    implementation process.
  • HIV/AIDS Late transfer of funds from National
    and late submission of business plans from NGOs
    delayed spending.
  • Forensic Pathology The unspent funds are
    reserved for the building of mortuary at
    Kerksdorp/Tshepong Hospital.

10
NW Department of Health
  • Receipt of maintenance plans late from DPW
    subsequent the reprioritization processes
  • Inconvenient procurement process- delayed payment
    processes.
  • Delays in finalising sites for clinics
  • Cancellation of contracts due to non performance
    of contractors.

11
NW Department of Sport, Arts and Culture
12
NW Department of Sport, Arts and Culture
  • The Community Library Services Grant spent a mere
    6 as a result of the late planning, tendering
    procedures, staff recruitment and training.
  • Spending on the Mass sport and recreation Grant
    seems problematic. The funds has apparently been
    divided between the departments new regional
    offices and no spending is taking place.
  • The spending on the archive building projects is
    significantly going well at 76.01 .
  • Department of Public Works is addressing the
    matter of Khuma library site that belonged to
    Health to allow spending on libraries.

13
NW Economic Development and Tourism
  • The none spending on MIDZ is as a result of the
    land issue for erecting MIDZ infrastructure.
  • The operating permit not yet approved by the
    Department of Trade and Industry (DTI) .

14
NW Department of Education
15
NW Department of Education
  • Low spending due to late delivery of HIV/AIDS
    material, spending has since improved.
  • Infrastructure grant delay in finalisation of
    budgets, reprioritisation of projects and plans,
    contractors are now on site.
  • Delays in finalisation of plans for sanitation
    and fencing of schools, projects are at tender
    stage.
  • Nine (9) projects for minor and major renovations
    have now started, the projects will be completed
    in 3 months time.

16
NW Department of Local Government and Housing
17
NW Department of Local Government and Housing
  • Low spending on Integrated Housing were as a
    result of the delay in registering contractors
    with NHBRC and this impacted negatively on the
    implementation and delivery of projects.
  • The zero expenditure on the Bucket replacement
    was due to the lack of readiness by
    Municipalities in terms of capacity.
    Municipalities has to first erect the structures
    and claim the funds from the department.
  • With regard to Disaster Management
    Municipalities were not readily available with
    the business plans and as a result no transfer
    payments could be made.

18
NW Department of Transport, Roads and Community
Safety
19
NW Department of Transport, Roads and Community
Safety
  • The low spending pattern on the infrastructure is
    due to reprioritization of projects and delays in
    the tendering processes.
  • Low spending on the EPWP and maintenance projects
    is due to transformation of the implementation
    of EPWP processes, hence project delivery was
    delayed.

20
NW Department of Public Works
21
NW Department of Public Works
  • Devolution of Property rates Taxes The 1st
    transfer from National will be effected only in
    August 2008, the total budget is R58 million.
  • Monitoring and evaluation on projects are being
    fast tracked due to implementation of IDIP
    delivery processes.
  • Slow spending on maintenance has been registered
    as a result of lack of capacity and poor
    communication between client departments and the
    agent. As a remedial measure, the IDIP focus will
    now be on maintenance.

22
NW Department of Social Development
23
NW Department of Social Development
  • Secure care centres under spending is due to the
    delay in finalizing the construction of the wall
    and the special fencing.
  • Substance abuse centre The purchase of a
    building for the substance abuse centre for
    in-patients will be completed in November 2008
    and renovations will be completed within three
    months thereafter.

24
NW Department of Agriculture, Conservation and
Environment
25
NW Department of Agriculture, Conservation and
Environment
  • The Department has spent 5 due to lack of the
    necessary capacity to design specifications and
    implement projects.
  • The tender for the outsourcing of the design of
    specifications and appointment of Engineers will
    be finalised in Septemeber 2008
  • The outsourcing the service will address the
    spending on Land Care Comprehensive
    Agricultural Support and Settlement Support.

26
Concluding Remarks
  • Although the total spending by the province seems
    to be fair, special attention has to be paid in
    addressing the spending on conditional grants and
    infrastructure.
  • At this point in time the province does not have
    any surplus funds to assist departments with
    budget pressures .
  • Provincial Treasury has set special meetings with
    MECs and Heads of Departments of the affected
    departments to address the issues of under
    spending of allocated budgets.
  • Monthly presentation and discussion of
    expenditure reports at Heads of Department
    meetings empowers departments to addressing the
    gaps that attributes to under spending.

27
Concluding Remarks
  • The rollout of the Infrastructure Delivery
    Improvement Programme (IDIP) within the province
    and the active involvement of the Provincial
    Treasury with the Provincial Departments of
    Education, Public Works and Health and the
    National Treasury definitely revealed positive
    results in the infrastructure planning, delivery
    and management.
  • The NW provincial treasury continues to meet
    provincial departments regularly to facilitate
    the acquiring of resources, requisite skills to
    improve budget planning and spending capacity and
    to address areas where there are risks of both
    over and under spending.

THANK YOU