Contra Costa Approach I: Initial Implementation of LID - PowerPoint PPT Presentation

About This Presentation
Title:

Contra Costa Approach I: Initial Implementation of LID

Description:

Sizing IMPs to manage hydrograph modification ... presenting calculations. Sample Outline and Examples ... Project size ( 1 acre impervious area must comply) ... – PowerPoint PPT presentation

Number of Views:45
Avg rating:3.0/5.0
Slides: 39
Provided by: danc1
Category:

less

Transcript and Presenter's Notes

Title: Contra Costa Approach I: Initial Implementation of LID


1
Contra Costa Approach (I)Initial Implementation
of LID
  • Tom Dalziel, Assistant Program Manager
  • Contra Costa Clean Water Program
  • Dan Cloak, P.E., Principal
  • Dan Cloak Environmental Consulting

2
Contra Costa Approach Afternoon Presentations
  • Experience So Far with LID(Tom Dalziel and Dan
    Cloak)
  • Sizing IMPs to manage hydrograph modification
    (Tony Dubin, Brown Caldwell)
  • Stream Classification Methodology (Andy
    Collison, Philip Williams Associates)
  • Next Steps in Implementation(Dan Cloak)

3
NPDES Permit New Development requirements
  • Treat runoff before discharge from site.
  • Match runoff peak flows and durations to
    pre-project conditions.
  • Cover or control sources of stormwater
    pollutants.
  • Maintain treatment facilities in perpetuity.

4
Cities, Towns, and County must
  • Incorporate requirements into their policies and
    processes for development review
  • Verify that on-site treatment devices are
    maintained
  • Prepare a Hydrograph Modification Management Plan
    to control future increases in runoff peaks and
    durations

5
Program Objectives
  • Comply with NPDES permit requirements.
  • Achieve reasonable protection of beneficial uses.
  • Minimize staff time required for additional
    project review.
  • Minimize costs to applicants.
  • Encourage smart growth and maintain economic
    competitiveness.
  • Adopt a flexible approach.
  • Encourage participation and consensus among
    interested parties.

6
Key Implementation Steps
  • Update to Model Stormwater Ordinance
  • Requires Stormwater Control Plan with Planning
    and Zoning Application
  • Adopted by each municipality countywide
  • Stormwater C.3 Guidebook
  • Workshops for municipal staff and land
    development professionals
  • Assistance with initial projects and preparation
    of examples

7
Stormwater C.3 Guidebook
  • Step-by-Step Approach to Compliance
  • How to Prepare a Stormwater Control Plan
  • Guidance for Selecting Treatment Facilities
  • Design Checklists and Standard Details for LID
    IMPs
  • Spreadsheet for Sizing BMPs and presenting
    calculations
  • Sample Outline and Examples
  • How to prepare an Operation and Maintenance Plan
    for treatment facilities
  • References and Hyperlinks to Design Resources

8
Stormwater Control Plan
Contents
  • Project Setting
  • Measures to Limit Imperviousness
  • Selection Design of Treatment BMPs
  • Source Control Measures
  • Permitting and Code Compliance Conflicts
  • BMP Maintenance
  • Construction Plan C.3 Checklist
  • Certification

9
Development Review
Pre-Application Meeting
Completed Application
Deemed Complete
Section Review
Conditions of Approval
Planning Commission
CEQA Review
Detailed Design
Plan Check
Permits to Build
10
Stormwater C.3 Compliance
Section staff may review planning zoning docs
for C.3
Pre-Application Meeting
Completed Application
Deemed Complete
Planning staff may determine if C.3 reqts are
addressed
Staff identifies general C.3 requirements
Section Review
Conditions of Approval
Planning Commission
CEQA Review
C.3 requirements attached to COAs
Detailed Design
Plan Check
Permits to Build
Staff reviews C.3 implementation in drawings
specs
11
Operation Maintenance
General descriptionof OM requirements
Detailed description and maintenance plan for
each facility
Certification of inspection continued
operation
Stormwater Control Plan
Stormwater Facilities Operation Maintenance
Plan
Stormwater Facilities Compliance Certificate
Submitted with Planning Zoning Application
Draft submitted with construction documents
Renewedeachyear
12
Results so far
  • Development community has responded positively
    to
  • Consistent ordinances countywide
  • Usability of Stormwater C.3 Guidebook
  • Workshops
  • Biggest Challenges
  • LID requires a different approach to drainage
    design
  • Resolving conflicts with public works standards
  • IMP ownership and maintenance responsibility

13
Low Impact Development in Contra Costa
CountyProblems and Solutions
  • Dan Cloak, P.E.
  • Dan Cloak Environmental Consulting

14
Implementing LID
  • Showing compliance with NPDES permit criteria for
    treatment
  • Designing effective IMPs
  • Residential Subdivisions
  • Street and drainage design
  • IMP operation and maintenance
  • Integrating with the HMP

15
Showing Compliance
  • NPDES Permit sizing criteria for treatment
    control
  • collect and convey drainage design
  • conventional, end of pipe treatment
  • use of runoff factors to determine design inflow
    or volume

16
Accounting for Pervious Areas
Conventional
LID
  • Self-treating areas
  • Zero discharge or self-retaining areas
  • Reduced runoff areas

17
Zero discharge areas
Conventional grading
Zero-discharge area
18
Zero-discharge areas
19
Example LID Site Design
20
Example LID Site Design
  • Make landscaped areas self-retaining

21
Example LID Site Design
  • Delineate areas that drain to each IMP
  • Decide where roofs will drain
  • Divide paved areas along grade breaks

22
Example LID Site Design
  • Fit IMPs into landscaping at low points of each
    drainage area

23
Example LID Site Design
  • Show each IMP is sized to treat runoff from its
    tributary area

24
IMP Design Gallery
  • Flow-through Planter
  • In-ground Planter
  • Bioretention Area
  • Vegetated or Grassy Swale
  • Infiltration Basin
  • Dry Well
  • Infiltration Trench

Indirect Infiltration

Direct Infiltration
25
Indirect Infiltration
Turf or planting
Planting medium
Gravel or drain rock
Perforated pipe
26
Sizing Criterion
0.2 inches/hour
BMP Area/Impervious Area 0.2/5 0.04
Planting medium
i 5 inches/hour
27
Flow-through Planter
28
Vegetated (Dry) Swale
29
Design Checklists
  • Vegetated Swale
  • Setbacks from structures
  • Sizing criteria
  • Minimum depth
  • Side slopes
  • Specification for imported soil
  • Specification for underdrain
  • Irrigation

30
Direct Infiltration
Dry Well
31
Residential Subdivision
32
Residential Subdivision
  • Suitably sized infiltration basin would require 3
    of 80 lots
  • Roofs, driveways, and landscaped areas drain to
    front yard swales
  • Streets drain to same swales

33
Seattle SEA Streets
34
Swales in Front Yards
  • Some jurisdictions prefer monolithic curb
    gutter
  • Access to parked vehicles
  • Avoid trip hazards
  • Standard location for public utilities
  • Still developing standard designs and
    maintenance responsibility

35
Curb and sidewalk
36
HMP Requirements
  • NPDES permittees must propose a plan
  • Manage increases in flow and volume where
    increases could
  • Increase erosion
  • Generate silt pollution
  • Impact beneficial uses
  • Post-project runoff may not exceed pre-project
    rates and durations
  • Option Equivalent Limitation
  • Account for expected stream change
  • Maintain or improve beneficial uses

37
Contra Costa HMP
  • Succinct standard, with four compliance options
  • Encourage Low Impact Development Integrated
    Management Practices (LID IMPs)
  • Allow proposals for stream restoration in lieu of
    flow control where benefits clearly outweigh
    potential impacts
  • No exemptions for
  • Project size (gt1 acre impervious area must
    comply)
  • Infill projects in highly developed watersheds
  • Project cost

38
Four Compliance Options
  • Demonstrate project will not increase impervious
    area
  • Implement pre-designed hydrograph modification
    IMPs
  • Use a continuous simulation model to compare
    post- to pre-project flows
  • Demonstrate increased flows will not accelerate
    stream erosion
Write a Comment
User Comments (0)
About PowerShow.com