Columbia River Basin Water Management Program Mill Creek Water Storage Feasibility Study Lake Roosev - PowerPoint PPT Presentation

1 / 13
About This Presentation
Title:

Columbia River Basin Water Management Program Mill Creek Water Storage Feasibility Study Lake Roosev

Description:

Drainage area 41 square miles. Estimated Annual runoff (A-F/mile) 425. Estimated Annual runoff (acre feet) 17,442. Mill Creek Storage Site ... – PowerPoint PPT presentation

Number of Views:85
Avg rating:3.0/5.0
Slides: 14
Provided by: HDR1
Category:

less

Transcript and Presenter's Notes

Title: Columbia River Basin Water Management Program Mill Creek Water Storage Feasibility Study Lake Roosev


1
Columbia River Basin Water Management Program
Mill Creek Water Storage Feasibility Study
Lake Roosevelt Forum April 13, 2009
2
WRIA 59 Colville River WatershedMill Creek Water
Storage
  • Project Applicant/Sponsor
  • Partially Prepared by

Stevens Public Utility District PO Box 592 Loon
Lake, Washington, 99148-0592 General
Manager/Engineer Dick Price, PE
HDR Engineering, Inc. 1001 SW 5th Avenue, Suite
1800 Portland, OR 97204-1134 Project Manager
Ron Mason, PE
With assistance from
Stevens County Watershed Planning
Office Courthouse Annex, 215 S. Oak St. Colville,
WA 99114 Project Manager Linda Kiefer
3
Mill Creek Water Storage Project Site
Mill Creek
Within the WRIA 59 Colville River Watershed
4
Drainage Area Map
Mill Creek Storage Site Watershed
5
Normal Annual Precipitation
Mill Creek Storage Basin-wide Mean Precipitation
36.2
6
Mill Creek Storage Site
  • Potential Project Purposes
  • Benefit for instream flows Low flow
    augmentation
  • Reduction of flooding
  • Benefit to current water users / water rights
  • Provide additional water to meet future water use
    needs
  • Micro-Hydropower opportunities

7
Mill Creek Hydrology
  • Stream Gages
  • USGS Stream Gage 12408500 41 years of record
  • Used for project analysis
  • Gage discontinued in 1986
  • WRIA 59 Stream Gage Project 2007 New Mill
    Creek Gage Installed
  • Site Information
  • Drainage area 41 square miles
  • Estimated Annual runoff (A-F/mile) 425
  • Estimated Annual runoff (acre feet) 17,442

8
Mill Creek Storage SiteElevation vs. Storage
Curve
9
Mill Creek Storage Project
Mill Creek Inundation
10
Mill Creek Storage Site
Major Study Elements
  • Biological and environmental coordination
    throughout the scoping process
  • Site survey
  • Develop project hydrology
  • Determine site location for spillway
  • Preliminary hydraulics to determine size type
    of spillway
  • Type size of regulating outlet
  • Geotechnical investigations

11
Mill Creek Storage Site
Major Study Elements, contd
  • Test pits soil samples
  • Lab testing of soil samples
  • Determine possible types of embankment
  • Construction quantities
  • Project alternatives analysis
  • Project drawings, (CADD)
  • Construction cost estimates
  • Project recommendation
  • Feasibility report
  • Quality control review

12
Mill Creek Storage Site
  • Current Project support
  • Conducted one scoping meeting with Department of
    Ecology Department of Fish and Wildlife on
    November 13, 2007
  • Stevens County Commissioners Stevens Public
    Utility District
  • Local Support of Colville River (WRIA 59)
    Watershed Water Resource Management Board
  • P.U.D. has option to purchase 40 acres where the
    structure would be located.

13
Questions??
  • Contacts
  • Richard (Dick) Price, General Manager, Stevens
    PUD _at_ (509) 233-8700
  • Ron Mason, Project Manager, HDR Engineering, Inc.
    _at_ (503) 423-3802
  • Linda Kiefer, WRIA 59 Watershed Project Manager
    Stevens County _at_ (509) 685-2832