LCLS Cavity BPM Production Status - PowerPoint PPT Presentation

About This Presentation
Title:

LCLS Cavity BPM Production Status

Description:

... Georo Braze Results: ... 1 Lower temperature braze (Orotin) and Induction heating ... Option 3 Braze window into a frame (Kovar) with similar expansion coef and ... – PowerPoint PPT presentation

Number of Views:64
Avg rating:3.0/5.0
Slides: 22
Provided by: hel85
Category:

less

Transcript and Presenter's Notes

Title: LCLS Cavity BPM Production Status


1
LCLS Cavity BPM Production Status
2
M1-Tool Works BPM Production
  • M1 awarded contract for machining bodies and
    transitions for 20 sets of parts
  • First Production BPM mechanical measured and
    Pre-lim cold test look very good

3
First production unit
4
Cavity Production Status
  • M1-Tool Works to deliver 11 units 1/22/08
    presently on schedule
  • Exercised the option for additional 20 units
    order from M1-Tool 1/08
  • Parts are on time and in spec so far

5
Cold Test Set-Up for Pre-Braze test
  • New production test fixtures for pre-braze
    testing
  • First production unit looks good and parts are at
    Altair waiting to be brazed

6
Cavity BPM Cold Test Data
7
First Production Unit Shipped to
  • Serial 010 shipped to Altair for brazing
    12/21/07
  • Unit pending complete braze due to window problem

8
Production Risks (Presented at FAC 10/30/07)
  • New End Cap design
  • New tuning scheme
  • Window plating problem
  • Unexpected integration problem
  • Unexpected vendor problem

9
The Window Braze Yield Problem
  • Problem brazing the window into the transition
    has caused delivery delay
  • Convergence and down-select of possible solutions
    pending
  • Concentration of effort critical

10
Understanding the Problem
  • History
  • Why were ALL the soldered units vacuum tight?
  • 15 for 15
  • Why did the units built for the 3-BPM work so
    well compared to present results
  • 6 small leaks, 9 good NO CRACKING

11
BPM Window Braze History
  • Prototype cold test unit, ITS test unit and 3-BPM
    test unit S/N 01 soldered Sn-Ag-Cu Vacuum tight
  • 2 test brazes Georo Vacuum tight
  • 3-BPM S/N R/0 first Georo braze Vacuum tight

12
Georo Test Braze before 3-BPM units
  • First test brazes clean and vacuum tight 5/12/07
  • No risk at this time so units for 3-BPM testing
    would be processed with Georo braze material

13
First Problem Window
  • 3-BPM test Ser 03 Georo Braze Results
  • 2 out of 5 leaked and the 2 that leaked had
    glossy Ni plating
  • 3-BPM test Ser 02 Georo Braze Results
  • 4 out of 5 leaked and the 4 that leaked had
    glossy Ni plating

14
Corrective Action from 3-BPM Window Failures
  • Start RD program to identify problem with bright
    Ni
  • CPI suggested using gold plating of first trials
  • First sample failed 10/07 because of apparent
    cracks and spattering
  • Possible cause was cool down too rapid

15
Window Problem Status 01/21/08
  • Moly retaining ring and retaining outer block
  • Lower temperature braze (Orotin) with induction
    heating re-work
  • CPI supplies transition with window installed
  • Kovar frame
  • Two piece transition
  • Bolt on window
  • Coax adapter

16
Cavity BPM Production Recovery Options without
changing the design
  • Option 1 Lower temperature braze (Orotin) and
    Induction heating re-work plan
  • Option 2 Work with CPI for a turn-key solution
    providing completed transition
  • Option 3 Braze window into a frame (Kovar) with
    similar expansion coef and weld into transition

17
Braze with existing/modified parts
  • PROs
  • Lowest risk option
  • Fastest recovery
  • Re-work plan possible
  • Lowest cost impact
  • No risk to qualified BPM system design
  • CONs
  • Yield not satisfactory
  • Re-work plan needs work

18
Induction Heating
  • Working with Ameritherm to re-work window after
    failed braze
  • Braze can be re-worked by applying additional
    paste or powder to joint

19
Receiver Electronics Production Status
  • All parts on order
  • Test fixtures developed
  • Parts to start arriving 2/08

20
Production Status
  • M1-tool Works delivered first unit 11/07 on time
    and in spec
  • First unit has been QA tested and cold tested
    with very good results
  • First unit is at Altair being Brazed less
    waveguide transitions
  • ANL to supply Altair with first set of modified
    window/transitions
  • Addition 11 BPMs in process at ANL

21
Production Milestones
  • Production of 1 BPMs for LTU 02/08
  • Production of 11 BPMs for undulator/LTU 03/08
  • Production of 12 BPMs for undulator 04/08
  • Production of 12 BPMs for undulator 05/08
  • Spares 4 BPMs 06/08
  • 40 sets of Electronics 08/08
Write a Comment
User Comments (0)
About PowerShow.com