Title: Gas Purchase and Sales Agreement Presented by Phumelele Madala Director, Edward Nathan Sonnenbergs
1Gas Purchase and Sales AgreementPresented by
Phumelele MadalaDirector, Edward Nathan
Sonnenbergs
2Brief Description of the Project
- Seller - South African Gas Supplier Limited
(SAGS) has - a concession licence from the Gas Regulator to
produce, transport and sell gas for 25 years - gas wells and will need to build a pipeline (to
be project financed) with capability of adding
compression to increase capacity and permit
multi-users - certified through experts that there are possibly
proven and probable gas reserves of up to 25 years
- Buyer is Coastal Energy Limited (CE) will
- buy the Gas in terms of a GSA from SAGS
- use the gas as fuel to fire a 600MW electricity
base load power plant in the Eastern Cape
3Schematic Diagram
4Legislative Framework
- National Energy Regulator Act, 2004 (No. 40 of
2004) - The Gas Act, 2001 (No. 48 of 2001) as well as its
- Piped Gas Regulations
5Legislative Framework
- The Regulations make further references to
compliance issues covered in other pieces of
legislation such as
- Promotion of Administrative Justice Act, 2000
(Act No.3 of 2000) - Promotion of Access to Information Act,2000 (Act
No.3 of 2000) - Employment Equity Act, 1998 (Act No. 55 of 1998)
- National Environmental Management Act, 1998 (Act
No. 107 of 1998)
6Key Principles for Gas Supply
- The key to procurement of fuel in any power plant
project must lie in the following 2 facts - The fuel supply must be firm, which implies
- Predictability in terms of price, quality,
quantity and - Consistency in terms of supply
- The fuel must, for environmental reasons, be
clean
7Terms of the Gas Supply Agreement
- Conditions Precedent
- SAGS
- to obtain all applicable Consents including for
trading and transportation of the gas - to issue a guarantee in favour of CE in respect
of both the quality and quantity of gas - CE
- to obtain all applicable Consents including for
trading, storage and distribution facilities - to issue a guarantee in favour of SAGS for
payment obligations
8The Term of the Agreement
- Usually directly linked to the availability of
gas reserves (Designated Gas Reserves) - SAGS has reserves of up to 25 years
- Either Party may undertake reserve calculations
and recalculations costs to be shares equally by
the parties - Term is 10 years from the Commencement Date with
an option to renew for a further 10 years
9Commencement Date
- To be achieved through a funnelling system.
- This involves a series of stepped down
notification periods to permit the commencement
date to be determined with certainty - The funnelling mechanism incorporates and takes
account of the activities and completion dates
for - - SAGS to complete pipeline construction
- - SAGS to prepare for delivery of commissioning
gas - - EPC to advise of plant completion date, and
- - OM to prepare OM activities
10Delivery Point
- Point where the SAGS pipeline links up with CEs
gas reception facilities - SAGS transports and delivers at its own costs and
risk up to this point - SAGS liability ends at CEs gas reception
facilities at the power plant - SAGS controls the flow and pressure of the gas at
this point - Title to, ownership (where payment has been
received), custody and risk of loss passes to CE - CE in charge of installing and maintaining its
reception facilities, including any fuel
conditioning equipment needed to ensure
compliance with OM requirements - SAGS to install and maintain fuel metering
equipment at the delivery point to measure the
quality and quantity of gas received - CE will have rights of access to measurement
equipment for verification of its accuracy - Delivery tolerances to be agreed as SAGS will
control the flow and pressure at the Delivery
Point
11Conditioning equipment
- Conditioning equipment includes, as a minimum,
all necessary temperature, pressure and
filtration plant, as well as any chemical dosing
or treatment facilities needed to effect storage
and operation - Thermal insulation and trace heating may have to
be installed by CE, where necessary, to -
- Such equipment would need to be designed in
accordance with recognised international
standards
- maintain the characteristics of the gas in
storage facilities to the standards required for
the operation of the power plant and - Prevent
damage from extreme ambient conditions
12Nominations and Variations
- CE to give 24 hrs notice of nominated quantities
of gas - Timing and method of communications and requests
to be specified - Aggregate of nomination per day shall not exceed
the Maximum Daily Quantity (MDQ), set at 110 of
the Daily Contract Quantity (DCQ) - Minimum threshold to apply to nominated
quantities of gas and set by SAGS
13Price
- The price to have the ability to pass through
costs to the off-taker through capacity (Capex
OM) and energy (variable OM) charge components - Price for the Gas at Commencement Date will be
ZAR equivalent to 1,50 per GJ - Price will be increased on each anniversary of
the Commencement Date by CPIX - Monthly invoicing and annual reconciliations
- Interest on late payments
14Supply of Gas
Take or pay
- SAGS has to ensure a secured and continuous sale
of a minimum amount of gas for the term of the
contract in order to meet its financial
commitment in respect of its own capital
expenditure and operating costs ie costs of
building the pipeline and operating same - CE on the other hand needs to ensure a sufficient
and adequate supply in order to ensure the power
plant is able to perform in accordance with its
dispatch instructions - Therefore the supply and demand of gas is subject
to a system where CE is obliged to receive a
total contract quantity over the term of the
contract TCQ and SAGS is obliged to provide the
TCQ - Take or Pay commitment is usually 90 of the TCQ
- CEs annual take or pay quantity commitment shall
be 90 of the adjusted ACQ
15(Cont) Supply of gas
The adjusted ACQ for each year shall be the
aggregate of the DCQs for that year minus
- Shortfall gas quantities
- Gas not delivered due to Force Majeure effecting
SAGS or CE - Gas not delivered due to Scheduled maintenance
reductions, and - Any permitted carry-forward gas from the
preceding year
16Further Supply Provisions
- Commissioning Gas - testing gas delivered prior
to the commencement date, price is usually
discounted and does not form part of CEs take or
pay commitment - Make-Up Gas excess gas paid for but not taken
during the year which CE may recover at a zero
contract price - Carry Forward Gas basically excess gas taken
by CE and carried forward to the next year - Excess Gas CE to pay where it may require
Excess Gas in a variation to a nominated delivery
quantity - Undertake or Overtake Gas- where CE under takes
or over takes at Delivery Point, has to pay a
premium - Off-Specification Gas- SAGS liable unless CE
accepted gas knowingly. If CE took unknowingly
then shall be deemed as Off-Spec Gas
17Scheduled Maintenance
- Scheduling of maintenance of Pipeline, Delivery
Point and Power Station, to be co-ordinated - Both parties relieved of obligations at this time
- Scheduled maintenance to be planned and agreed
between the parties up to six months in advance
18Force Majeure
- Customary Force Majeure provisions and exclusions
to apply - Definition to include reservoir failure relief
and unforeseeable damage or destruction to the
pipeline - CE may purchase gas from a third party during the
subsistence of a Force Majeure event
19Exclusivity
- SAGS shall not supply gas from the designated
reserves to any other party without the consent
of CE - CE shall not acquire gas from any other party
other than with the consent of SAGS
20Termination Events
- Non-delivery and non-receipt for a continued
period of six months - Force Majeure event subsisting for continuous
period of six months - Failure to deliver by SAGS for a continuous
period of four months - Failure to accept delivery for a continuous
period of four months - Failure by CE to make payment
- If the conditions precedent are not fulfilled by
an agreed longstop date - Any other non-remedial breach by the Parties
21Miscellaneous Provisions
- Warranties and Representations
- Change in Control of both parties
- Applicable Law
- Taxes
- Confidentiality
- Costs
- Insurances
- Notices
- Dispute Resolution etc
22Schedules
Proposed schedules to the agreement may include
- Delivery Point Schedule
- Supply Area and Designated Reservoirs Schedule
- Measurement Schedule
- Gas Specification Schedule
23Conclusion
- Risk identification, analysis and mitigation is
crucial - Its important to understand the whole project
value chain including the structure and funding - Its important to act as a reasonable and prudent
project participant - A Gas supplier should aim to commercialize its
gas reserves and be aware that a buyer will
attempt to match GSA terms with downstream
commitments
24Thank You