Title: Indian Reservation Road Bridge Program 23 CFR 661


1
Indian Reservation RoadBridge Program23 CFR 661
  • IRRCC Meeting
  • February 22, 2006
  • Tulsa, Oklahoma

2
This Presentation will cover
  • Status of IRRBP
  • Projects
  • Funding
  • Update to the 23 CFR 661
  • IRRBP Regulations

3
IRRBP Projects Funded in FY 05
  • 45 bridge projects funded
  • 17 BIA owned projects
  • 28 Non-BIA owned projects
  • 22.8 million used
  • 19 million TEA-21 bridge funds
  • 3.8 million of FY 05 STEA funds
  • 9.2 million rolled back to the IRR Program

4
SAFETEA-LU FY05 IRRBP Funding
  • 14,000,000/yr per SAFETEA-LU
  • Net 11,970,000
  • (lost 2,030,000 due to 14.5 ob limit)
  • carried over into FY 06

5
FY 06 IRRBP Projects(as of 2/15/06)
  • 20 bridge projects funded
  • 4 BIA owned projects
  • 16 Non-BIA owned projects
  • 10.1 million used
  • FY05 Carryover Funds
  • 1.87 million remaining

6
Status of IRRBP Funding in FY 06
  • 14 million for FY 06
  • Net 12.06 million after Ob limit and rescission
  • 1.87 million remaining from FY 05 carryover
  • Total available 13.93 million

7
Changes to IRRBP
  • Result from SAFETEA-LU
  • 14,000,000 for FY05 through FY09
  • Use to carry out planning, design, engineering,
    preconstruction, construction, and inspection of
    projects
  • Bridges must be structurally deficient or
    functionally obsolete
  • Funds for design based on availability
  • Funds for construction and inspection after PSE
    approval.

8
Update to the 23 CFR 661 IRRBP Regulations
9
Issues
  • How to handle Preliminary Engineering?
  • Should the 80 - 20 split for BIA and non-BIA
    owned bridges be kept?
  • Is 1st come - 1st served basis working?
  • Should there be a funding ceiling for design and
    construction?

10
Annual IRRBP Funding
11

FY 06 IRRBP FUNDING FOR DESIGN

12
FY 06 IRRBP FUNDING FOR CONSTRUCTION

13
Update to the 23 CFR 661 IRRBP Regulations
  • Whats new?
  • Definitions PE, PSE, Approach roadway
  • Eligibility Criteria
  • Contents for an application for PE
  • Whats Next?
  • Looking for comments/recommendations from BIA and
    IRRCC. (Due by March 10)

14
Update to the 23 CFR 661 IRRBP Regulations
  • Then What?
  • Review comments, prepare Interim Final
    Regulation, and provide to IRR Coordinating
    Committee
  • Publish Interim Final and request public comments
  • Review comments and prepare Final Regulation
  • Publish Final Regulation

15
QUESTIONS?
  • Russell Garcia, P.E.
  • IRR Program Engineer
  • Federal Lands Highway
  • Washington D.C.
  • (202) 366-9815
  • russell.garcia_at_fhwa.dot.gov