Title: Module Production ___________ Report on the Catania Status
1Module Production___________ Report on
theCatania Status
Salvatore Costa Università di Catania and INFN
Sezione di Catania
2Outline
- Module accounting
- Bonding
- Production rate
- Bonding experience
- Pull Test results
- Failure analysis
- ARCS LT Tests
- ARCS test analysis
- LT test analysis
- Usage of central DB
- Logistics transportation of modules
3Module Accounting
Module Type? Total IB34 IB12phi
Received from Bari Gantry 61 28 33
Bonded 58 (51 in DB) 27 30
ARCS tested 56 (47 in DB) 27 29
OK 53 26 27
bad 3 1 2
LT tested 49 (0 in DB) 27 22
OK 49 27 22
bad 0 0 0
4Production Rate
- Initially slow due to bonding commissioning (we
lacked long-standing experience with previous
bonding jobs), but now on schedule. To illustrate
our progress - First box received, with 8 Modules, was completed
(bonded ARCS tested) 23 days after arrival - Last 2 boxes, with 9 Modules each, have both been
completed within 2 working days after arrival - Current bonding capability is 4-5 Modules/day
- Long Term keeps up with no difficulty with
current incoming flux of 1 9-Module box / week
5Bonding Experience
- Became full-blown Bonding Center on 5 Dec 2003
- Previously designated Bond Repair Center
- Had passed official CMS Qualification Tests
(bond test 1 2) - Bonding experience with previous experiments
none - Equipment
- 2 Hughes 2470-II bonders
- 1991, 1987
- automatic but no Pattern Recognition or
- bond foot deformation feedback
- 1 ATV GM-100 pull tester
- manual
- Machine downtimes each time a new machine fault
occurred that we had not seen before. - Time spent to learn to locate the source of
the fault, what action to take and with what
procedures.
Higher probability of bond failures or accidents
6Bond Pull Tests Results
IB34
IB12phi
sampling
5g
7Bond Failure Analysis
53 Modules 34048 bonds repaired repaired repaired repaired unrepairable unrepairable unrepairable unrepairable
53 Modules 34048 bonds modules affected strips affected modules affected channels affected
Totals 44 84 563 1.65 10 19 29 0.08
Machine failures 42 80 506 1.48 7 13.2 14 0.04
Bond foot misplacement 2 3.8 9 0.026
to stick 42 80 506 4 7.6 4 0.012
Pinholes (caused by bonding?) 1 1.9 1 0.003
Operator mistakes 2 3.8 57 0.17 3 5.7 15 0.04
Mishandling 1 1.9 7 0.02 2 3.8 7 0.02
Wrong ref 1 1.9 50 0.15
Wrong par (lifts, pinholes) (1) (1.9) (384) (1.11) 1 1.9 8 0.02
8Bond PA-Sen in TIB L12
correct
misplaced
9ARCS Test Analysis
- All tests performed following the official TIB
procedure - ARCS 7.0 used for long time (7.1 installed
operational but not yet fully tested) - Tonys macro used initially, starting mid March
Riccardos update (now v3.1.0) - Flagging efficiency with Riccardos macro
100 - Out of 53 good modules, 51 are grade A, only 2
are grade B - No IV problems
- A total of 55 defective strips found over 34048
bonded strips - 29 caused during bonding
- 26 pre-existing Sen pinholes APV-PA bond opens
Hyb faulty chan
open
chan
10ARCS Analysis IV
We wrote a script which queries DB to compare
measured IV with the Sensor one. We also
implemented Temperature correction. NO IV
problems up to now
IV data not available for all the sensors
11Long Term Test Analysis
- 49 modules tested with TIB Official Scenario
(about 72 h) - Some modules retested with a 1-night scenario due
to failure on the last record - First, cold last records always recorded
- Some failures of the sw before Marcos patch on
I2C - 1 failure due to DAQ problems with Lt_1.22
- No failures since Lt_1.24 was installed
- Riccardos macro used for the analysis (now
v3.1.0) - No new defective strips appeared after LT test
- From time to time some noisy strips appear and
disappear
123 Bad Modules
- In 3 Modules, all from the very last group of
Modules received, we have observed plain failure
of the ARCS Test after bonding (they had passed
with flying marks the test upon arrival) - 2 Modules (30200020035289, 303) fail Fast Tests
Low Voltage test I(V2.50) 850 mA (max 750 mA) - Bonds are among the best weve made, both
mechanically and aesthetically - No visually evident damage from possible
mishandling - ESD?
- 1 Module (30200020035305) fails to power up the
Hybrid - Damage to connector?
- Has something changed in our working environment
or procedures? - All these modules Hybrids are marked with Alans
blue dot - Deep investigation needed to understand these
problems
13Usage of central DB
- Bonding data always timely uploaded to TrackerDB
since the beginning - for all ARCS LT data, xFLAG 1.4.3 has been used
to produce XML files 53 ARCS 49 LT - XML files checked for consistency with root files
and macros output - No serious problems reported
- Only few root files need to be redone due to old
ARCS bug in the header - 86 of ARCS XML files already uploaded
- LT XML files not yet uploaded
14Logistics Transportation
- No major problems with modules received from Bari
- In first 2 boxes only the styrofoam blocks on the
sides were too far apart, so Modules (on
transport cradles) slipped out of their slots,
but no damage to the modules resulted. Problem
was quickly corrected in newer boxes - Some dirt (mainly small fabric? fibers)
- We blow a 1.5 atm air jet on Module before
starting visual inspection - Our storage space in clean room can hold 8 more
boxes (72 Modules), - After, better to start shipping to Pisa
- or we will have to figure out how to carve out
more storage space
15ARCS LT Test
The Catania CMS Module Production Crew
Inspection, Test on arrival, Bonding
S. Costa, N.Giudice, F.Noto, F.Raimondo,
C.Sutera, C.Tuve
S. Albergo, M. Chiorboli, M. Galanti, G. Gatto,
A.Tricomi