IES 303 Chapter 14: Aggregate Planning

Description:

4. Level #2: constant Layoffs, building antici- Hiring, depleting antici ... 3. Level #1: constant No layoffs, building No hiring, depleting ... – PowerPoint PPT presentation

Number of Views:61
Avg rating:3.0/5.0
Slides: 19
Provided by: KarndeeLe4
Category:

less

Transcript and Presenter's Notes

Title: IES 303 Chapter 14: Aggregate Planning


1
IES 303 Chapter 14 Aggregate Planning
Week 9 January 5, 2006
  • Learning Objectives
  • Understand the concepts and methods of aggregate
    planning
  • Formulate and solve capacity planning problem

2
Aggregate Plan
  • Aggregate Plan A statement of a companys
    __________ _________, _____________, and
    _________ holding based on estimates of customer
    requirements and capacity limitations
  • Service Industry
  • _______________
  • Regarding staffs and labor related factors
  • Manufacturing Industry
  • _______________
  • Regarding production rates and inventory

3
Aggregate Production Planning (APP)
  • Determines resource capacity to meet demand
  • For intermediate time horizon, 6-12 months
  • Not feasible to build new facility
  • May be feasible to hire/lay off workers,
    overtime, or subcontract
  • _______________ OR _______________

4
How should an aggregate plan fit with other plans?
Figure 14.1
5
Aggregate Plan Managerial Inputs
6
Aggregate Plan Outputs
Aggressive Alternatives
Complementary Products
Competitive Pricing
Reactive Alternatives





7
Aggregate Planning Objectives
  • Minimize Costs/Maximize Profits
  • Maximize Customer Service
  • Minimize Inventory Investment
  • Minimize Changes in Production Rates
  • Minimize Changes in Workforce Levels
  • Maximize Utilization of Plant and Equipment

8
Examples of Capacity Adjustment to Meet Demand
  • Producing at a constant rate and using inventory
    to absorb fluctuations in demand
  • Hiring and firing workers to match demand
  • Maintaining resources for high demand levels
  • Increase or decrease working hours (overtime and
    undertime)
  • Subcontracting work to other firms
  • Using part-time workers
  • Providing the service or product at a later time
    period (backordering)

9
Planning Strategies
  • ____________________
  • Match demand during the planning horizon by
    either
  • Vary workforce or vary output rate
  • ____________________
  • Maintain a constant workforce level or constant
    output rate during the planning horizon
  • Constant workforce or constant output rate
  • ____________________
  • Combined several strategies

PURE STRATEGIES
10
Pure Strategy
What are pros / cons of these strategies?
11
1. Chase 1 vary workforce Layoffs Hiringlevel
to match demand
2. Chase 2 vary output Layoffs,
undertime, Hiring, overtime,rate to match
demand vacations subcontracting
3. Level 1 constant No layoffs, building No
hiring, depletingworkforce level anticipation
inventory, anticipation inventory,
undertime, vacations overtime,
subcontracting, backorders, stockouts
4. Level 2 constant Layoffs, building
antici- Hiring, depleting antici-output rate
pation inventory, pation inventory, over-
undertime, vacations time, subcontracting,
backorders, stockouts
12
Aggregate Planning Costs
  • _______________________
  • _______________________
  • _______________________
  • _______________________
  • _______________________

13
Ex 1 Candy Company
  • Given the following costs and quarterly sales
    forecasts of a candy company, compare the two
    strategies
  • Strategy 1 Level production with constant
    workforce level
  • Strategy 2 Chase production by varying workforce
    level

14
Transportation Method
  • A method of LP
  • Gather all cost info into one matrix
  • Try to obtain the lowest cost alternative

15
Notations
  • It inventory at the end of period t (I0
    beginning inventory)
  • h holding cost per unit per period,
  • r regular production cost per unit,
  • o overtime cost per unit,
  • u undertime cost per unit
  • s subcontracting cost per unit,
  • b backordering cost per unit per period
  • Rt regular-time capacity in period t
  • Ot overtime capacity in period t
  • St subcontracting capacity in period t
  • Dt forecasted demand for period t
  • U total unused capacities

16
Tableau Method
  • Step 1 Put all capacities from the total
    capacity column into the unused capacity column.
    Next, put unit costs in each of the small boxes
  • Step 2 In column 1 (period 1), allocate as much
    production as you can to the cell with the lowest
    cost but do not exceed the unused capacity in
    that row or the demand in that column.
  • Step 3 Subtract your allocation from the unused
    capacity for the row. This quantity must never be
    negative.

17
Tableau Method (Contd)
  • Step 4 If there is still some demand left,
    repeat step 2, allocating as much production as
    possible to the cell with the next-to-lowest
    cost. Repeat until the demand is satisfied.
  • Step 5 Repeat steps 2 through 4 for periods 2
    and beyond. Take each column separately before
    proceeding to the next. Be sure to check all
    cells with unused capacity for the cell with the
    lowest cost in a column.

18
Ex 2 Transportation Method
  • Given the following costs and quarterly sales
    forecasts, use the transportation method to
    design a production plan.
  • What is the total cost of the plan?