GERBER Timing. Anode. machine time = 2,5hours. adjustment time (machine ... During 1 shift (7,5 hours) Gerber able to make: 1 set : 1Anode 1 cathode (ME234/2) ... – PowerPoint PPT presentation

Number of Views:35
Avg rating:3.0/5.0
Slides: 6
Provided by: yuriypisc
Category:

less

Transcript and Presenter's Notes

Title: Yuriy Pischalnikov, EMU CMS Production Meeting Aug25,1999


1
Milling CSC at GERBER machine Timing Issues
  • Results of Timing
  • of Milling 5 Anode Panels
  • at GERBER Machine.

2
Timing MACHINE TIME
3
Timing(Cathode) Machine Idle TIME
4
Timing(Anode) Machine Idle TIME
5
SummaryGERBER Timing
  • Anode
  • machine time 2,5hours
  • adjustment time (machine idle regime) 2,5hours
  • Total 5 hours for anode
  • Cathode
  • machine time 1 hours
  • adjustment time (machine idle regime) 1 hours
  • Total - 2 hours for cathode
  • During 1 shift (7,5 hours) Gerber able to make
  • 1 set 1Anode1 cathode (ME234/2)
  • 5 set per week 12/3 Chamber (ME234/2)