Title: presented to ISM Workshop, Aurora, Colorado
1Preparation and Executionfor a Chief of Defense
Nuclear Safety(CDNS) Review
- presented toISM Workshop, Aurora, Colorado
- September 12, 2006
- Bob Brandhuber
- Senior Manager, ESH
Sandia is a multiprogram laboratory operated by
Sandia Corporation, a Lockheed Martin
Company,for the United States Department of
Energys National Nuclear Security
Administration under contract DE-AC04-94AL85000.
2Keys to Success
- Early review of CDNS instructions and other site
reports - Team
- Site Office and Contractor
- Maintained separation of responsibilities and
authority - Clearly identified responsible individuals
- Accountability and empowerment
- SSO Site Manager appointed a project leader
- SNL President appointed a project leader
3Keys to Success (continued)
- Technical expertise
- Team of functional area experts analyzed CDNS
Criteria Review and Approach Documents (CRADS)
and led self-assessments - 50 SSO, SNL corporate, and SNL line staff
- 50 functional area experts tapped
- Organization
- Project planner
- Focus
- Meetings
- Verify flowdown of requirements
- Code of Federal Regulations, DOE Orders,
corporate practices to Members of the Work Force
(MOW)
4Eight Months of Preparation
- Weekly SSO and SNL meetings
- Held teams accountable
- Tracked action items
- Maintained momentum
- Exchanged ideas
- 33 self-assessments identified deficiencies
before review began - Corrected some
- Corrective action plans in place for remaining
deficiencies
5Preparation Key to Success
- Self-assessment reports
- Stoplight charts
- Binders
- Complete
- Tailored
- 1 GB thumb drives with information
- Dedicated and thoroughly equipped conference room
- Preparation team available and involved in review
6Self-Assessment Reports
- Measured SSO and SNL compliance with requirements
- Documented deficiencies and disposition
- Provided to CDNS review team before arrival
- SSO received credit for self-identified issues
- Self-assessments were critical to success!
7Stoplight Charts
Risk Evaluation
CRAD Element Status
red
green
yellow
8Binders
- Agenda
- SSO oversight responsibilities, SNL nuclear
operation description, safety briefing
information - Organization charts, Sandia maps, local eateries
- Functional area/CRAD points of contact matrix
(handout)
- Relevant audits and self-assessment findings and
corrective action plans - 25, four-inch binders
- Planning and resources
9Thumb Drives
- Held review documents, e.g., SSO and SNL
documentation, ESH manual excerpts, radiological
protection procedures manual, etc., - Facilitated updating information
- Eliminated reams of paper
- Required special handling because UCNI and OUO
were included - 25, 1 GB drives were provided, tracked, and
returned
10Review Team Conference Room
- Outfitted with tables, chairs, computers,
printers, phones, copier, shredder, microphone,
projector, electronic white board, office
supplies - Staffed with SSO and SNL personnel to answer
questions, provide information, resolve problems,
address issues, etc. - Working area for review team
- Location of daily debriefs
11SSO and SNL Responsibilities
- SSO
- Interfaced with CDNS and SNL counterparts
- Gathered information requested by CDNS team
- Scheduled interviews requested by CDNS team
- Participated in daily outbriefs
- SNL
- Interfaced with SSO counterparts
- Gathered information requested by SSO
- Scheduled interviews requested by SSO
- Attended daily outbriefs
- As a team, SSO and SNL
- Assessed performance against each CRAD
- Identified areas for improvement
- Took appropriate actions during inspection
- Team!
12Results
- 3 areas received Noteworthy Practices
- 13 areas received Meets Expectations
- 5 areas received Needs Improvement
- Comments attributed to CDNS review team members
- Sandia had thorough self-assessments
- Stoplight charts provided a good overview
- Sandia was the most prepared site setting a new
standard - Logistics were commendable
- Transparency and assistance were much appreciated
- Letter of appreciation from Patty Wagner, SSO
Manager to Tom Hunter, SNL President, listing
over 50 SNL personnel who contributed to the
effort
13Lessons Learned Recommendations
- Start early!
- Encourage and maintain communication between Site
Officeand Contractor - Identify points of contact for each functional
area - Continue and standardize functional areas
self-assessments - Commit resources for adequate logistics it is
worth the investment - Demonstrate effective flowdown of contract
requirements - Develop and implement methodology to correct
findings, weaknesses, deficiencies,
observations, and opportunities for improvement
14Measures of Success
- The leader of the 19 member CDNS Review team told
us during pre-visit out-briefing that Sandia Site
Office was the most prepared of all the sites
they have visited to date setting a new standard. - Patty Wagner
- SSO Site Manager
- May 1, 2006
- This review included 18 functional areas for
nuclear facilities across the SNL/NM complex.
Thirteen of the areas were rated as Meets
Expectations . . . - Patty Wagner
- SSO Site Manager
- July 10, 2006
15Questions
16Points of Contact
- SSO Project Leader Kim Davis
- (505) 845-4392
- kadavis_at_doeal.gov
- SSO Project Planner Jeff Petraglia
- (505) 284-4961
- jpetraglia_at_doeal.gov
- SNL Project Leader Bob Brandhuber
- (505) 845-1237
- rbrandh_at_sandia.gov
- SNL Project Planner Glenn Buchfeller
- (505) 844-5759
- gwbuchf_at_sandia.gov