PERT and CPM, Resource Allocation, GERT MT 246 Module 11 - PowerPoint PPT Presentation

1 / 61
About This Presentation
Title:

PERT and CPM, Resource Allocation, GERT MT 246 Module 11

Description:

Paths near the Critical Path with Large Variance may become critical ... Impossible to Level Requirements for all Resources. Minimize Conflicts ... – PowerPoint PPT presentation

Number of Views:1447
Avg rating:3.0/5.0
Slides: 62
Provided by: andyd6
Category:

less

Transcript and Presenter's Notes

Title: PERT and CPM, Resource Allocation, GERT MT 246 Module 11


1
PERT and CPM, Resource Allocation, GERTMT 246 -
Module 11
2
Topics Covered Previously
  • Schedule Parameters
  • Critical Path
  • Early Expected Time
  • Latest Allowable Time
  • Total Slack
  • Free Slack
  • Time Based Networks

3
Criticisms of Network Methods
  • Unrealistic Results
  • Assume Project can be completely defined (not
    true) they evolve
  • No Clean line between activities (precedence
    helps)
  • Precedence relationships are not fixed (do-loop
    may be necessary, I.e., test)
  • They do produce the best schedule possible

4
Alternative Schedule Networks
  • Program Evaluation and Review Technique (PERT)
  • Incorporates uncertainty into schedule estimates
  • Critical Path Method (CPM)
  • Explicitly includes cost as a scheduling
    consideration
  • Graphical Evaluation and Review Technique

5
Program Evaluation and Review Technique (PERT)
  • Utilizes three time estimates for each activity
  • Optimistic, a
  • Most Likely, m
  • Pessimistic, b
  • Beta Probability Distribution Function for Each
    Activity
  • Calculates Expected Time, t
  • Calculates Variance, V

6
Estimating Activity Time
7
Probability of Finishing by A Target Completion
Date
  • Expected duration of project T is the sum of
    expected Activity times on Critical Path
  • Variation in the Project Duration Distribution is
    the sum of the variations of the activity
    durations on the Critical Path

8
Pert Network with Expected Activity Times and
Variances
9
PERT Advantages/Disadvantages
  • Allows sensitivity analysis to determine
    probability of finishing the project on time
  • Does not account for Near Critical Path
  • Extremely complicated
  • Cannot account for errors in schedule logic or
    the ability of project manager to alter schedule
    logic via workarounds
  • Bottom Line No better than MS Project and a lot
    more complicated!

10
Z Values for the Normal Distribution
11
Near-Critical Paths
  • PERT is overly Optimistic
  • Paths near the Critical Path with Large Variance
    may become critical
  • Probability of Completing All Paths is the
    Product of Probability on each Path

12
Meeting the Target Date
  • Actions to Shorten to Project
  • Move Activity on the Critical Path to a Parallel
    Path
  • Add or transfer resources,from activities with
    large slack to critical or near-critical
    activities
  • Substitute less time-consuming activities or
    delete those that are not of utmost importance

13
Criticisms of Target Date Actions
  • Paralleling Activities can be risky, failure of
    one can hurt the other
  • Adding or transferring resources to speed
    activities increases cost and denies resource
    leveling
  • Substitution or Elimination can degrade end-item
    Performance, Requirements, Poor Quality of Work

14
Simulation of PERT Network
  • Uses Monte Carl Methods to show the Near-Critical
    Path Sensitivity
  • Procedure gives an Average Project Duration and
    Standard Deviation (Variance) which is more
    realistic than simple PERT
  • Returns Probabilities ff Other Paths Becoming
    Critical
  • Allows Historical Data

15
Activities and Time Estimates from Evans and Olson
16
Project Network from Evans and Olson
17
Crystal Ball Simulation Results
18
Criticisms of PERT
  • Assumes Activity times can be Accurately
    Estimated and are Independent
  • Three estimates are guesses, not necessarily
    better than one guess
  • Contractual Arrangements Influence Time Estimates
  • Activity Times are not Independent ( Constant
    Energy Surface)
  • Conflict of necessary Resources

19
Criticisms of PERT (Continued)
  • Leads to Overly Optimistic Results
  • Looking only at Critical Path Misleading
  • Near-Critical Paths must be Considered
  • The Beta Distribution Gives Large Errors in
    Estimating T
  • Errors in T come from faulty time estimates

20
Critical Path Method (CPM)
  • DuPont Company (1957), a Plant Construction
    Project
  • Gives Primary Emphasis to Cost
  • Deterministic
  • Only One Time Estimate is Used
  • Mathematical Procedure for Trade-off between
  • Project Duration
  • Project Cost
  • Analysis of resources
  • Trades between Activities to Minimize Duration
    and Cost

21
Time-Cost Relationship
  • Assumes that the estimated completion time for an
    activity can be shortened by adding resources
  • All activities are assumed to be performed at the
    normal work pace
  • Normal Cost is associated with Normal Work
    Pace
  • Normal work pace is the most efficient and
    therefore least costly
  • Faster than normal work pace adds cost

22
Time/Cost Relationship of an Activity
23
Reducing Project Duration
  • CPM model can be utilized to shorten the project
    completion time
  • Allows tradeoff of penalty of schedule slip vs.
    cost of adding resources
  • Time/Cost relationship allows determination of
    the cost of shortening a given activity
  • Reducing an activity increased its cost
  • Can be made anywhere on the critical path
  • Minimized by selecting the activity with the
    smallest slope

24
CPM Time-cost Tradeoff
25
Reducing Project Duration (Continued)
  • Step 1
  • Reduce A by one week to 21 weeks adds 2K to the
    Project Cost
  • Does not change CP
  • Step 2
  • Reduce A by one more week to 20 weeks adds 2K for
    a total of 59K
  • Slack in Path B-E us used
  • Two CPs

26
Reducing Project Completion Time
27
Reducing Project Duration (Continued)
  • Step 3
  • Reduce A and E by one week to 19 weeks adds 4K to
    the Project Cost 63K
  • Reduces A to 6 Weeks (crash)
  • Step 4
  • Slack time on C-F is 3 weeks
  • Reduce G by 3 weeks( one week beyond crash) to
    16weeks adds 15K for a total of 59K
  • Slack in Path C-F us used
  • All Paths become CPs

28
Reducing Project Completion Time
29
Reducing Project Duration (Continued)
  • Step 5
  • Must shorten all three CPs
  • 1 Week from E, D, and C
  • Project is 15 weeks
  • Project cost is 86K
  • C is at Crash

30
Duration Reduction and Associated Cost Increase
31
Shortest Project Duration
  • Performed Step-by-Step the activities to speed up
    to reduce the Project Completion Time
  • Eventually leads to the shortest possible Project
    Duration and Cost
  • Shortest Possible Project Duration Crash all
    Activities at Once
  • Fig 8-8 Duration 15 wks cost 104K
  • Not necessary to Crash every Activity to achieve
    shortest Time

32
Example Network Using Crash Times
33
Shortest Project Duration (Continued)
  • 15 Weeks is time on CP
  • Stretch time along non CP
  • Path B-E-G has 5 weeks slack
  • Three weeks added to B
  • Two Weeks to E
  • One week to D
  • 104K - 3(3K) -2(2K) - 1(5K) 86K
  • Crash all, then stretch NC activities with
    greatest slope, use all slack to obtain minimum
    cost

34
Total Project Cost
  • Add Indirect to Activity Costs to Obtain TPC
  • Assume an Indirect Formula
  • Overlay the Indirect and Direct to Obtain the
    Total Project Cost
  • Consider Contractual Incentives
  • Penalty
  • Bonus

35
Total Time-Cost Tradeoff
36
Time-Cost Incentives
37
CPM Advantages/Disadvantages
  • Does not deal with influence of indirect costs
    and contractual incentives
  • Dealing with these parameters increases schedule
    complexity
  • Assumes that time and cost are linearly related
  • Plausible but unproven in practice
  • Overridden by Uh-Ohs!
  • Cannot account for errors in schedule logic or
    the ability of project manager to alter schedule
    logic via workarounds

38
CPM Advantages/Disadvantages (Continued)
  • Bottom Line No better than MS Project and a lot
    more complicated!

39
Microsoft Project
  • Will be used for Estimating and Scheduling home
    work assignment due in late April
  • value is 100/250 points for Homework Grade
  • If your CD, which was included with your
    Textbook, license has expired
  • Recommend Ordering 60 day Trial CD from Microsoft

40
MS Project Re-Order
  • Ordered 10 Trial CDs for Class Use
  • Or You MayPoint Web Browser to MS Project Home
    Page and Order your own Copy
  • http//www.microsoft.com/products/msoffice/project
    /
  • Click on Order Trial CD radio button
  • Follow instructions
  • 10 Day delivery
  • You Pay SH about 6.00

41
MS Project Near Term Assignment
  • Install software from Trial CD, if not available
  • CD is available for lt6.00
  • Go over tutorials
  • Try some of the homework examples
  • Change dependencies to see the effect
  • Do homework on MS Project
  • Not required
  • Will help on later assignments

42
Scheduling with Resource Constraints
  • Constrained Resource Related Problems Involve
  • Labor
  • Capital
  • Equipment
  • Material
  • Consider two Resource Relate Problems
  • Resources are Balanced
  • Resources are Available

43
Resource Loading and Leveling
  • Resource Loading
  • Quantity/Amount necessary to conduct Project
  • Changes throughout the Project
  • Usually low the peak then low
  • Problem for Functional Manager
  • Solution is Resource Leveling
  • Juggle activities
  • Delay or Split Activities to Achieve Smoothing

44
LOGON Project Weekly Labor Requirements
45
Worker Loading for the LOGON Project
46
Resource Loading and LevelingContinued
  • More Uniform Loading if Activity could be Split
  • Once defined as Activity this can be a problem
  • Changes
  • Budgets
  • Costs accounting Structures
  • Schedules
  • Other Control Mechanisms
  • Most SW Packages and PDM Permit Splitting

47
Smoothed Worker Loading for the LOGON Project
48
Resource Loading and Leveling Continued
  • Leveling Easily Applied to Any Single Resource
  • Difficult with Many Resources
  • Impossible to Level Requirements for all
    Resources
  • Minimize Conflicts
  • Smooth loading for Priority Resources
  • Human Resources are Given the Highest Priority

49
Equipment Loading for the LOGON Project
50
Resource Loading and Leveling Continued
  • The Four Options Are
  • Delaying Activities
  • Eliminate Some Work Segments or Activities
  • Substitute Less Resource-Consuming Activities
  • Substitute Resources
  • Cons
  • Most Qualified Workers not Available
  • Reduces Scope/Quality of Work-Project Performance

51
Constrained Resources
  • Activities Cannot Consume all Working Capital or
    Pieces of Equipment
  • Differs from Resource Leveling in that more
    attention is given to Maximum Availability
  • Sometime Rescheduling or Delay is required until
    Resources are Available

52
Schedule and Worker Loading with a 14 Worker
Constraint
53
Constrained Resources (Continued)
  • Constrained Resources forces scheduling
    activities for immediate or delayed until assets
    are available
  • PM Scheduling SW Employ a Heuristics (Procedure
    Based on a Rule) for making the Decision
  • ASAP
  • ALAP
  • Most Resources
  • Shortest Task Time
  • Least Slack

54
Constrained Resources (Continued)
  • No single Rule works (always) better than another
  • Use Variety in Combination to Obtain best
    Schedule
  • Available Scheduling SW use only One or Two
    Methods (You can do better by trial and
    replace)I.e.,
  • Reduce the level of resources per Activity
  • Split the Activities
  • Alter the Network

55
Multiple Project Scheduling
  • Multiple, Concurrent Projects from a Matrix Pool
    of Equipment and Skilled Workers
  • Construction
  • Consulting
  • Systems Development
  • Maintenance
  • Maintain a minimum, Uniform Level Personnel and
    Other Resources (Smoothing)

56
Graphical Evaluation and Review Technique (GERT)
  • Similar to PERT in Many Ways
  • Allows Alternative Time Distributions
  • Allows Looping Back of Activities
  • If a test is failed, can be rescheduled
  • New Symbols to Represent a large Variety of
    Situations
  • Complex Nodes, Activities into and Paths from
  • Probabilistic
  • Branching

57
Graphical Evaluation and Review Technique (GERT)
  • ROSEBUD Project Expanded to include failure of
    the Tests
  • Hardware Test means Adjustments to Equipment
  • System Test means change any or all of
  • Installation
  • Redesign of Hardware
  • Re-spec SW
  • User Test
  • Major of Minor System Adjustments
  • System Test

58
ROSEBUD Expanded Network
59
GERT Network for ROSEBUD Project
60
Next Lecture
  • Cost Estimating and Budgeting
  • A billion here and a billion there. Pretty soon
    it starts to add up to real money. Senator J.
    Everett Dirkson, Democrat from Illinois

61
Diagramming and PERT, CPM Homework Assignment
  • Homework Assignment Worth 50 Points
  • Nicholas Ch 7, Questions Ch7-10a, 11a, 13b, 15a
    and c, 19
  • Nicholas Ch 8, Questions Ch8-10, 11, 14
  • Due on March 27, 2001
Write a Comment
User Comments (0)
About PowerShow.com