Title: NLC Accelerator Physics
1NLC Accelerator Physics
- NLC Machine Advisory Committee
- SLAC
- October 4th, 2000
2Outline
- Recent progress
- Layout and optics
- Structure design
- Beam delivery systems
- Vibration program
- Simulations / modeling
- Outstanding issues
- Source modeling
- Damping ring
- Beam based alignment issues
- High luminosity operation
- System-wide tolerance calculations
- System-wide studies (tuning, beam tails, MPS)
- Plans
3Accelerator Physics Issues in NLC
- Two issues
- Energy (rf technology)
- Luminosity (small spots beam power)
- Beam power (long bunch trains)
- charge from sources
- long-range wakefields
- Small spot sizes
- low emittance damping rings
- final focus system
- alignment and jitter tolerances
- beam-based alignment and feedback
- Both issues (very high charge densities)
- beam collimation and machine protection
4NLC Project Scope
- Injector Systems
- Main Linac
- Housing with all internal services
- Half filled for initial 500 GeV cms
- Upgrade by adding rf, water, power to the 2nd
half of the tunnels - Beam Delivery (high energy IR)
- Two BDS tunnels and IR halls with services
- some components must be upgraded to get from 1
TeV to 1.5 TeV
1.5 TeV 0.5 - 1.0 TeV (1.5 TeV withincreased
gradientor length) 1.5 TeV(length will
support a 5 TeV FFS)
5IR Layout Issues
- Final focus aperture is set by low energy beams
??1/?? but magnet strength is limited by highest
energy operation - Final focus has limited energy range without
rebuilding magnets and vacuum system - Simplify design by dedicating one IR to low
energy operation and one to high energy
operation - Low energy range of 90350? GeV (build arcs
for lt500 GeV?) - High energy range of 2501000 GeV
- Need to specify reasonable ranges!
- High energy beamline would have minimal bending
to allow for upgrades to very high collision
energies - High energy BDS could be upgraded to multi-TeV
operation!
6Dual Energy IR Layout
Site roughly 25 km in lengthwith two 10 km linacs
Optional low energy IP92-350 (500??) GeV
Possible staged commissioning
Low energy (50 - 175 GeV) beamlines
e
e-
Return lines production and possibly drive beam
-share main linac tunnel
High energy IP0.25-5.0 TeVupgraded in stages
Centralized injector systempossibly for TBA
drive beamgeneration also
7Status of Dual Energy IRs
- Optics for high energy CD0.4 BDS updated as of
9/00 - Studied muon backgrounds in high energy IR
- more aggressive but looks OK at 1 TeV and 109
particles collimated with two muon spoilers - No studies on low energy BDS
- simple scaling from Big Bend arc suggests bending
is not an issue - ?arc ? E?3/2 for constant Ncell and De
- Final focus system should be straight-forward
- Studying round beam capabilities of new FFS for
g-g IR in either low or high energy IR - To deliver luminosity simultaneously to both IRs,
need to duplicate end-of-linac emittance
diagnostics and collimation
8180 Hz Operation Issues
- 180 Hz operation is decoupled from low/high
energy IR - two options 180 Hz at 500 GeV or ?120 Hz at 500
GeV and 60? Hz at lower (250 GeV) energy - Choice depends on AC power
- Primary issues are
- power consumption, average heating and radiation
- machine protection (60 Hz minimum operation for
any low e beam) - emittance generation
- duplicate BDS beam lines for dual energy
operation - Damping redesign is an opportunity to ease design
- either two identical rings or optimize each of
two rings for damping and emittance, respectively - probably 200 meter circumference with reduced
wiggler lengths
9Centralized Injector
- Discussing different options
- sharing linac tunnels
- accelerating multiple bunch trains in one
accelerator - see John Sheppards talk
- Studied BD for multiple bunch train acceleration
- much easier than SLC!
- trains separated by filling time (1ms at S-band)
- requires damped structures at S-band and probably
L-band - still operational issues to resolve
- Have parameters for bunch compressors etc. but no
optics and need further study of transport
10Parameters for 500 GeV and 1 TeV
11Low Energy IR Luminosity
12Possible 1.5 TeV Parameters
- Two cases considered initially
- doubled rf power
- 50 increased length
- Both cases ac power limited to ? 200 MW
- Higher energy parameter sets are based on the
CLIC parameter sets and require lower emittance
beams and smaller IP spot sizes
13Multi-TeV Collider Facility
- Need improvements in rf technology to make higher
energy cost effective - multi-beam klystrons, active rf pulse
compression, or TBA - Need high gradients to keep length reasonable and
balance cost of rf system - At 35 MV/m (SC max gradient), 3 TeV linac would
be 110 km - Optimum gradient in NLC is between 75 and 100
MV/m depending on how components scale with rf
power - Normal conducting cavities with lower cost rf
system and higher gradient of 100 ? 200 MV/m - Need very small beam emittances and small spots
to achieve luminosity injection complex similar
to present NLC - Reuse next-generation LC injection system and
beam delivery, and use linac tunnels with
modified components
14Multi-TeV Energy Upgrade
- High energy FFS could support multi-TeV
collisions if we deliver the beams (not true of
present energy collimation) - Beam parameters studied as part of CLIC project
- significantly smaller beam emittances and spot
sizes - similar average currents with smaller bunch
spacing - slightly shorter bunches
- need to verify these parameters
- In addition to rf systems, would have to upgrade
low emittance generation and diagnostics - Need to consider the likely options to avoid
precluding a upgrade route!
15Structure Design ? Wakefields
- Short-range wakefields depend on average iris
radius - To avoid BBU structures must cause the long-range
transverse wakefield to decay in a few bunches - Four different configurations
- Detuned (DS) - this tends to be insufficient for
long bunch trains because of the re-coherence (OK
at L-band and S-band) - Damped-Detuned (DDS) - route followed by SLAC
based on a detuned structure with weak damping
imposed by coupling to a manifold that runs along
the cells which also serves as BPM. Heavily
Damped (HDS) - route followed by CERN and
Shintake where every cell is directly damped.
Has reduced shunt impedance and possible pulsed
heating problems. - Medium Damped (MDS) - combine local damping with
detuning may provide a good compromise!
16Structure Design
- Injector linac beam loading compensation based on
DT - simplifies rf systems
- match filling time to maximum beam current
- Optimized injector linacs for large apertures and
low wakefields - thicker irises and higher phase advance per cell
(135 or 150 deg.) - Injector linacs based on RTOP design rather than
rounded cells -- simpler parameterization with
similar performance - L- and S-band linacs based on detuned design
but C-band needs damping either DDS or MDS
17S-Band phase advance options
Struct Type t/a1 favd Ncell F1 Tf aave/? GL a RD
S 6.8/4.8 120 114 4.03 592 0.143 17.08 b RDS 6.8/4
.8 120 114 3.94 429 0.156 13.54 c RDS 8.5/5.5 120
114 3.94 509 0.154 15.83 d RDS 9.5/6.0 120 114 3.9
4 579 0.153 16.45 e RTOP 8.0/ - 135 102 3.93 546
0.156 16.42 f RTOP 9.0/ - 135 102 3.92 578 0.157 1
6.63 g RTOP 9.0/ - 135 102 3.93 600 0.156 16.83 h
RTOP 6.5/ - 150 92 3.92 633 0.158 16.83
6 structure/module, 120 MW per module rf power
- Started with RDS structure case (a)
- Needed to be close to zero-crossing for LR
wakefield case (d) - Better performance and simpler RTOP structure
with 135 case (f)
18L-band Structures
- RTOP cell profile
- Filling time optimized to e booster parameters,
6-structure/module. - T (thickness) optimized to maximize amin
- (adjusting R such that GLVbooster/Lacc at full
power) - GL for the e booster 12.5 MV/m.
19C-band Linac Pulse Compression
- SLED-I Q0100000
- Klystron power 65 MW
- Klystron pulse 3.7 ?s
- Module 2 klystron, 4 structures
- DLDS
- Klystron power 65 MW
- Klystron pulse/bin 0.5 ?s
- Module 8 klystron, 32 structures
20C-band Injector Linac
- Tolerances are tight (similar to X-band)
- 70 looser tolerances with DLDS-like system
because of shorter fill time and larger iris
radius but higher cost (John Sheppard) - Need further optimization on different pulse
compression techniques
21Injector Linac Tolerances
- Tolerance estimated for a maximum of 10
emittance dilution - One-to-one trajectory correction in e- booster,
e drive linacs - Beam based alignment similar to main linac in
pre-linacs - Short-range wakefields limit trajectory and
structure alignment - Long-range wakefields impose cell-to-cell
alignment - Alignment tolerances in ?m
22X-band Structures
- RF damage problem appears to correlate with group
velocity - Choose 150 degree phase advance to reduce vg
- Use thicker irises to further reduce vg and the
surface field - Improved coupler design reduces fields in
couplers - Same rf power to 6m girder produces the same
acceleration - 25 fewer cells per linac but more couplers
- Two options studied thus far
- L 1.4 m, vg0 6.5, 4 structures per 6m girder
- L 0.9 m, vg0 4.4, 6 structures per 6m girder
- Studying the dipole wakefields - may require MDS
- Looking at pulsed heating of MDS and DDS
structures
23X-band Structure Parameters
1500/cell RDDS1
24Dipole Damping versus Shunt Impedance
- Strong damping such as the choke- mode
structure or the CLIC HDS have more than
20 reduction in the Rs - LIAR studies indicate that Qs of 750
are OK - Pulsed heating is another limitation at
the damping waveguide irises
25RF Pulsed Heating
Peak ?T ? 40C in RDDS ? 70C in MDS with
a dipole Q of 250
MDS structure with standing wave
26Short-Range Wakefield Calculations
- Linac tolerances are dominated by short-range
wakefields - Single bunch energy spread is compensated by
running 11 off-crest and the BBU is treated
with BNS damping - Short-range wakefield models are based on mode
summation for periodic structures with extension
for high frequencies - Measurements on the SLAC linac agree with the
longitudinal wakefield calculations at the 10
level - Correction for group velocity as noted recently
at CERN will be more important for NLC
structures - Linac parameters are chosen so wakefield impact
on the transverse dynamics is 25 of that in the
SLC - Measurements of transverse wakefield in SLAC
linac are started
27Long-Range Wakefield Calculations
- Long-range wakefield models are based on two band
circuit models for the lowest dipole band - Parameters from OMEGA3P modeling of cells
- Very good modeling of RRDS1 rf and wakefield
measurements at ASSET - Starting to model 150 degree MDS structures at
FNAL and SLAC (KEK) - Studying higher dipole bands - visible in RDDS1
- Parallel time-domain calculations using TAU3P -
10 cells calculated recently - full structure
calculations soon
28RDDS1 ASSET Measurements
- Wakefield model (with errors) for RDDS1 agree
well with measurements
- Lowest band is around 15 GHz
- Next band (25 GHz) is visible after 1.4 ns
29Wakefield Calculations
- Circuit model has been used to study structure
internal alignment and frequency tolerances for
RDDS1 - Tolerances are set by detuning and are expected
to be similar in MDS and DDS - to be verified - Alignment tolerances
- structure alignment is determined by short-range
wakefield - cell-to-cell alignment is determined by
beam-based alignment requirements and by
long-range wakefields - cell-to-cell alignment also limited by
bookshelf effect - Frequency tolerances
- fundamental is set by phase error through
structure and net energy gain - dipole frequency tolerance is set by long-range
transverse wakefield - frequency errors break the
detuning scheme causing BBU and growth of the
projected emittance
30Beam Delivery Status
- Working on the collimation system (Peter
Tenenbaum) - Pre-linac collimation (provides MPS functionality
and cleans tails) - Bunch length collimation in BC2
- Post-linac collimation (provides MPS
functionality and cleans tails) - Collimation in final focus
- Need to update beam halo and tail calculations
- Consumable collimator work is progressing nicely
- Collimator wakefield experiment has some great
data! - New design for final focus (Pantaleo Raimondi)
- Much shorter length (design is still evolving)
- Scales to high energy very nicely (700 meters for
5 TeV collisions) - Background studies are being performed
- Need to study full BDS performance
- Present high energy BDS is 2.5 km instead of 5 km
per side
31Vibration Program
- Vibration program (Andrei Seryi)
- Extensive measurements of slow motion
- strong correlation with pressure
- explanation for site dependence in diffusive
(ATL) motion - separate out systematic motion from diffusive ATL
motion - Studying cultural sources and interaction with
tunnels - SLD pit has nearly acceptable vibration
- SLD detector is quite noisy
- Integrated model for whole spectrum including
fast wave motion, ATL, and systematic motion - Working at including localized cultural sources
- Implementing model in LIAR for feedback and
beam-based alignment studies - Organizing GM2000 in November
32Simulations and Code Development
- Optics and modeling codes (MAD, DIMAD, and LIAR)
in good shape (except for space charge effects) - Structure and wakefield calculations in good
shape - Ground motion model is being developed (Andrei
Seryi) - Feedback simulations being compared with SLAC
linac performance - Parallel FBII code, code development on ECI -
need exp. comparisons - Parallel version of LIAR but need somebody to
drive this program - No progress on full system tuning simulations
- No progress on tolerance calculations
33Outstanding Issues
- Source modeling
- Damping ring
- Beam-based alignment issues
- High luminosity operation
- System-wide tolerance calculations
- System-wide studies (tuning, beam tails, MPS)
34Electron / Positron Sources
- Sources (John Sheppard and David Schultz)
- Polarized electron gun suffers from current limit
- SLC positron target damage being investigated
- Brute force can be used in both cases
- Need to understand yield and capture better
- Polarized rf gun would simplify damping ring
design - Looking at alternate e sources (undulator and
laser based systems) - Radiation / beam tails
- Significant limitation from sources ? DR (60 kW
beam power) - Post-DR tails will be removed in pre-linac and
post-linac collimation systems (Peter Tenenbaum) - Pre-DR collimation systems are not defined
- Need modeling of source beams with space charge
and wakefields
35Damping Rings (John Corlett)
- Damping rings are similar to 3rd generation light
sources - ex0 is 1/3 of ALS normalized emittance
- ey0 is 1/150 of ex0 (extracted emittance is 50
larger) - tolerances are 100 to 50 mm
- impedance issues are thought understood
- many issues have also been demonstrated at the
KEK ATF - Concerns
- new instabilities electron cloud instability
(ECI) and fast beam-ion instability (FBII) - large current dependence observed at ATF
(intrabeam scattering?) - heavy reliance on wiggler damping (aperture and
other issues?) - extreme sensitivity of collider to instabilities
36Structure Alignment
- The average alignment of the cells in the
structure is set by the short-range wakefield - Present emittance budget allocation is 50 in
NLC-IIb ? 10 ?m structure alignment - Structures MUST be aligned using beam derived
information - Use 3 S-BPMs along structure -- resolution is few
?m - S-BPMs must represent average alignment of the
structure - With 3 S-BPMs cell-to-cell alignment must be
better than 9 ?m assuming a random walk model - Long-range wakefield in DDS (or MDS?) set a
tolerance of 3 ?m cell-to-cell alignment assuming
a random walk model - Even this looks possible!
37Beam-Based Alignment Hardware
38Quadrupole Alignment (Nan Phinney)
- The quadrupole alignment is set by the dispersion
error - Present emittance budget allocation is 40 in
NLC-IIb ? 2 ?m quadrupole alignment - Quadrupoles MUST be aligned using beam derived
information - Tolerance corresponds to roughly 100 ?m
dispersion error (dispersion is not exact in
linac with varying energy spread) - With 1 ?m BPM resolution, 100 ?m dispersion not
so bad! - Desire very local correction (align every
quadrupole perfectly) with a procedure that does
not interrupt luminosity - May not work with (permanent) quadrupole center
shifts - Investigating alternate routes (DF steering,
e-bumps, ballistic corr.)
39Beam-Based Alignment Hardware
- Stripline BPMs for FFTB have 1mm resolution
and rf cavity BPMs have 40nm resolution
- Stripline BPM-Quad centers shift but 20 mm
over 2 years
40Beam-Based Alignment Hardware
- Movers developed for Final Focus Test Beam
(FFTB) have steps lt0.5mm - Alignment procedure at FFTB with statistic
errors of few mm - FFTB dispersion measurements set upper bound
on alignment ?5? statistic errors
Vertical quad-to-bpm alignment 12/95 and 6/96
41Beam-Based Alignment Studies
- Measure quadrupole center shifts (how accurately
can this be done) - Re-visit DF steering alignment procedures
- Study systematic effect of rf deflections
- Study technique of changing energy upstream of
alignment region - Study effectiveness of e-bump procedures
- Bumps used in SLC to reduce emittance dilution by
factor of 10 - Three diagnostic stations along linac to
facilitate e tuning - Study stability of e-bump solutions
- Re-balance emittance budgets depending on
performance - Study interaction of beam-based feedbacks, ground
motion and alignment - include terrain following!
42Parameters for 500 GeV and 1 TeV
43Route to High Luminosity in NLC
- NLC design has built-in margins to cover nominal
operating plane including 50 charge overhead and
300 emittance dilution - NLC damping rings spec. to produce 0.02 mm-mrad
although design requires 0.03 mm-mrad - SLC used emittance bumps to reduce emittance
dilution from 1000 to 100technique not
included in NLC emittance budgets - Use margins to achieve higher luminosity
- Present prototypes and RD results are better
than initial specs (see RDDS cell frequencies and
structure alignment S-BPM) - ??y lt 25 in linac if production rf components
are similar to prototypes - Both will lead to increased luminosity (34?1033
at 880 GeV)
44RDDS1 Structure Construction
- RDDS1 cells were designed at SLAC and machined at
KEK final machining performed on
diamond-turning lathe - Attained excellent resultsfrequency errors less
than 1 MHz, i.e. lt1?m errors - Tolerances for dipole modefrequencies are 5
times looser! - Bonding process still needsto be understood!
45High Luminosity Issues
- High luminosity operation was first described at
Snowmass 96 but as something to be attained well
after initial operation, i.e. long learning curve - Presently there is pressure to verify high
luminosity operation is possible from the
beginning - Need to perform study on beam bumps to verify
effectiveness (no question in simple simulation!)
and rebalance emittance budgets - Need to verify that all requirements are being
treated consistently for high luminosity
operation although without the conservatism that
is presently used
46System-wide Tolerances
- Tolerances have been updated in piece-wise manner
- Review of tolerances presented at May
Collaboration / MAC meeting - Last systematic update was ZDR in 1996!
- Too many tolerances to update individually!
- Most of collider is linac / transport line
- Possible to generate program to calculate
tolerances from lattice deck and simple inputs - Must be verified with lots of detailed tracking
- Creating tracking program for linac and BDS (in
collaboration with Ralph Assmann at CERN) - Requires implementation of tuning techniques
47System-wide Simulation Studies
- For simulations, collider can be broken into
three sections - sources (upstream of damping rings)
- capture efficiency beam tails multi-bunch
loading - linac dynamics non-relativistic beams bunching
- damping rings
- capture efficiency dynamic aperture collective
instabilities beam-based alignment - storage ring dynamics nonlinearities collective
instabilities - linacs and beam delivery
- dynamic aperture collective instabilities
beam-based alignment and feedback beam tails - linac dynamics bunching nonlinearities time
evolution
48System-wide Simulation Studies
- Have tools for storage ring dynamics (lots)
- Have tools for linac dynamics (LIAR, ELEGANT?)
- Have tools for BDS (DIMAD , ELEGANT?)
- Have tools for bunch compression (but 6-D is
slow) - Need to generate a combined program for linac /
BDS - Need tool to study interaction of feedbacks,
ground motion and beam-based alignment - Do not need source ? IP simulations ever
- Do not need DR ? IP simulation in the near term
49FY01 Tasks
- Tolerance studies, parameter budgets and BB
alignment - Verify consistent parameters for high luminosity
operation - Re-evaluate beam tails and loss models for BDS
and injector - Re-evaluate DR optics and instability
calculations - Continue ground motion and isolation studies
- Continue collimator wakefield experiment
- Continue low vg structure development
- Continue optics development to support costing
exercises - Need to increase staff - budgeted for 2.5
additional people in FY01 and 4 more in FY02