TRANSMISSION SYSTEM OVERVIEW - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

TRANSMISSION SYSTEM OVERVIEW

Description:

Three blades at top of each tower, each 110 feet in length ... Blades turn a shaft connected to the rotor of an electric generator ... – PowerPoint PPT presentation

Number of Views:85
Avg rating:3.0/5.0
Slides: 12
Provided by: DTS57
Category:

less

Transcript and Presenter's Notes

Title: TRANSMISSION SYSTEM OVERVIEW


1
New Mexico Transmission System Overview
TRANSMISSION SYSTEM OVERVIEW NETWORK OPERATING
COMMITTEE April 17, 2007
2
Efficient Use of Existing Transmission System
  • Long-term weather study (8 weather stations)
  • Increased rating (18) of transmission lines by
    using less conservative wind speed assumptions
  • Real-time monitoring
  • Installed monitoring equipment to allow for
    temporary increase of emergency ratings based on
    actual (as opposed to worst-case) temperature and
    wind conditions
  • Traveling Wave Fault Recorders on all 230kV,
    345kV line and key 115kV lines
  • Disturbance Monitors
  • Bulk transformer online monitoring (oil,
    temperature, hot spots)
  • Risk management (Video Sagometers)
  • Several lines exposed to low-probability,
    short-duration events have been rated for
    high-temperature operation

3
Efficient Use of Existing Transmission System
4
Efficient Use of Existing Transmission System
  • Reactive Compensation Voltage Support
  • Series compensation of 345 kV lines
  • Shunt capacitors
  • Albuquerque power factor control (RCCS)
  • Transmission Line Clearance
  • Over 1500 miles of transmission lines have been
    phase-raised to remove ground clearance
    limitations.
  • Emergency Procedures
  • Automatic load shedding schemes, as safety net
    measures, to handle deficiencies in transmission
    capability during peak usage during scheduled
    maintenance and forced repairs
  • Reactor contingency scheme

5
WECC/NERC Criteria
6
Generation InterconnectionsA Few Facts
  • Received 50 generation interconnections since
    2000 (42 direct interconnect and 8 are joint
    studies)
  • Signed 6 LGIA for a total of 768 MW
  • 451 MW Wind
  • 317 MW Gas and Bio Mass
  • Todays Queue
  • 5 Feasibility Studies
  • 6 System Impacts Studies
  • 4 Facility Studies
  • 1562 MW Wind
  • 1479 MW Gas and Combined Cycle

7
New Mexico Wind Energy Center
  • Located in Eastern New Mexico
  • 204 MW capacity
  • Supplies up to 20 of PNMs total demand at any
    given time
  • Supplies approximately 3.5 on the average
  • Installed in 2003, in record time!
  • Owned and operated by FPL Energy
  • PNM purchases markets all the output

8
Technical Specifications
  • 136 towers, each 210 feet tall
  • Base circumference is gt 40 feet!
  • Wind Farm spread out over 15 miles
  • Three blades at top of each tower, each 110 feet
    in length
  • Facility feeds power onto nearby PNM high-voltage
    transmission line

9
How Wind Turbines Produce Energy
Person on top of rotor
  • Blades rotate toward the wind
  • Winds of 6 to 7 mph are enough to turn blades
  • Blades turn a shaft connected to the rotor of an
    electric generator
  • Mechanical components can withstand winds of up
    to 55 mph

10
NMWEC Power Output Pattern
11
Questions?
Write a Comment
User Comments (0)
About PowerShow.com