Title: Florida High Speed Rail Authority Update for Orange County Board of County Commissioners
1Florida High Speed Rail Authority Update
forOrange County Board of County Commissioners
2OUTLINE
- Timelines and Federal Processes
- Floridas Strong Position - Previous HSR Work
- Approach for Florida Response to Stimulus
- FDOT Participation
3High Speed Rail on National Agenda
- Competition for High Speed Rail start-up around
the US - Federal Bills
- October 08 Bill 1.5 billion over 5 yrs (not
yet appropriated) - Stimulus 09 Bill 8 billion added 100
Federal Funding no State match required (fully
funded) - Future additional Bills anticipated due to
national importance placed by Obama
Administration
4CORRIDORS COMPETING FOR BILLIONS OF FEDERAL
5Federal High Speed Rail Corridors
- Northeast Corridor
- California Corridor
- Empire (NY) Corridor
- Pacific Northwest Corridor
- South Central Corridor
- Gulf Coast Corridor
- others may emerge
- Chicago Hub Network
- Florida Corridor
- Keystone (PA) Corridor
- Northern New England Corridor
- Southeast Corridor
6(No Transcript)
7Floridas Strong Position
- Over the past 10 years
- 1998 Florida Overland eXpress
- Tampa-Orlando-Miami environmental and engineering
- 2004 Florida High Speed Rail Authority
- PDE for Tampa-Orlando
- Feasibility study for Orlando-Miami
- Approximately 30 million invested in both these
efforts
8Florida High Speed Rail Authority 2004
ORLANDO
TAMPA
9Review of Tampa-Orlando Corridor
- Two major components of FHSRA work
- PDE for Tampa-Orlando corridor
- Procurement of Design-Build-Operate-Maintain
Finance vendor
10NEPA Work Completed
- FRA Record of Decision (ROD) completes NEPA
- ROD required to advance into Final Design
11Design-Build-Operate-Maintain Finance- DBOMF
- RFP issued October 2002
- Investment Grade Ridership Study Issued Nov 2002
- Beachline (then Beeline) route
- Total riders 2.4 to 2.8 million Revenue 39
-42 mill - Greeneway route
- Total riders 3.8 to 4.1 million Revenue 54-
56 mill - Both proposing teams committed to covering
Operations Maintenance costs based on inclusion
of the Choice and Captive markets
12DBOMF SUBMITTALS
- FLUOR-BOMBARDIER
- Jet-Train Technology Gas Turbine
- Double track Disney to OIA, single track to Tampa
- Firm Fixed price of 2.056 Billion
- GLOBAL RAIL CONSORTIUM
- Electric TGV Technology
- Double track entire system
- Firm Fixed price of 2.4 Billion
- F-B was ranked first on 6-2 vote
- Negotiations proceeded until August 2004
13ORLANDO MIAMI FEASIBILITY 2004
14Orlando-Miami Feasibility FHSRA 2002
- Key Findings for Tampa-Orlando-Miami
- Operating Ratios (2020)
- Will revenues from system cover OM costs?
- For 180mph Operating Revenue 531 mill
- OM Costs 174 mill RATIO 3.05
- Benefit-Cost Ratios (30 year NPV)
- Do Benefits to Society for building this system
justify the costs? - For 180mph RATIO 1.95
- Conclusion
- Overall benefits of this system greatly exceed
costs
15APPROACH TO RESPONSE
- Highlights of Proposed Response
- Corridor Tampa-Orlando-Miami
- P3 Approach
- Green Technology
- Includes Stimulus component shovel ready
CREATES JOBS!
16Corridor Definition
- Tampa-Orlando-Miami Corridor is logical
- Much work done on entire corridor
- Entire corridor is designated by FRA
- Phasing to logical intermediate stations
- Provides 180 mph capability
- Reasonable total length (310 miles) compared to
other competing corridors - LA - San Francisco is almost 400 miles
- Boston - DC is 440 miles
17Public Private Partnership
- Private partner is critical for success
- Leases system for long term
- Shares profits in excess of defined thresholds
- A single system approach is logical
- Single technology
- One set of standards that is interoperable
statewide - WILL REQUIRE ASSUMPTION OF OM RISK BY PRIVATE
PARTNER
18GREEN TECHNOLOGY ELECTRICALLY DRIVEN SYSTEM
- State of the Art examples
- Siemens Velaro Alstom AGV
19Stimulus Approach
- Sequence of work
- Define Minimum Operating Segment (MOS) with FRA
within the Tampa-Orlando corridor - Obtain Record of Decision for MOS
- Start construction of MOS
- Incrementally add segments on
- Continue environmental work on next segments
- GOAL MOS can start construction in 18 months
20Board Meeting of April 2
- FDOT Letter of Assistance
- Offered to take over the application process for
stimulus funds to use in-house resources - FHSRA accepted offer, with three requests
- 4 million federal funds available to FHSRA from
4 years ago - FDOT to report status in 2 weeks - FDOT to provide progress report at future
meetings - FHSRA requested that institutional memory
available be used - Sunrail FHSRA passed a support resolution 4-1
21Florida High Speed Rail Authority Update
forOrange County Board of County Commissioners