Florida High Speed Rail Authority Update for Orange County Board of County Commissioners - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Florida High Speed Rail Authority Update for Orange County Board of County Commissioners

Description:

Florida High Speed Rail Authority Update for. Orange County Board ... Beachline (then Beeline) route: Total riders: 2.4 to 2.8 million; Revenue: $39 -$42 mill ... – PowerPoint PPT presentation

Number of Views:183
Avg rating:3.0/5.0
Slides: 22
Provided by: adrian70
Category:

less

Transcript and Presenter's Notes

Title: Florida High Speed Rail Authority Update for Orange County Board of County Commissioners


1
Florida High Speed Rail Authority Update
forOrange County Board of County Commissioners
  • April 7, 2009

2
OUTLINE
  • Timelines and Federal Processes
  • Floridas Strong Position - Previous HSR Work
  • Approach for Florida Response to Stimulus
  • FDOT Participation

3
High Speed Rail on National Agenda
  • Competition for High Speed Rail start-up around
    the US
  • Federal Bills
  • October 08 Bill 1.5 billion over 5 yrs (not
    yet appropriated)
  • Stimulus 09 Bill 8 billion added 100
    Federal Funding no State match required (fully
    funded)
  • Future additional Bills anticipated due to
    national importance placed by Obama
    Administration

4
CORRIDORS COMPETING FOR BILLIONS OF FEDERAL
5
Federal High Speed Rail Corridors
  • Northeast Corridor
  • California Corridor
  • Empire (NY) Corridor
  • Pacific Northwest Corridor
  • South Central Corridor
  • Gulf Coast Corridor
  • others may emerge
  • Chicago Hub Network
  • Florida Corridor
  • Keystone (PA) Corridor
  • Northern New England Corridor
  • Southeast Corridor

6
(No Transcript)
7
Floridas Strong Position
  • Over the past 10 years
  • 1998 Florida Overland eXpress
  • Tampa-Orlando-Miami environmental and engineering
  • 2004 Florida High Speed Rail Authority
  • PDE for Tampa-Orlando
  • Feasibility study for Orlando-Miami
  • Approximately 30 million invested in both these
    efforts

8
Florida High Speed Rail Authority 2004
ORLANDO
TAMPA
9
Review of Tampa-Orlando Corridor
  • Two major components of FHSRA work
  • PDE for Tampa-Orlando corridor
  • Procurement of Design-Build-Operate-Maintain
    Finance vendor

10
NEPA Work Completed
  • FRA Record of Decision (ROD) completes NEPA
  • ROD required to advance into Final Design

11
Design-Build-Operate-Maintain Finance- DBOMF
  • RFP issued October 2002
  • Investment Grade Ridership Study Issued Nov 2002
  • Beachline (then Beeline) route
  • Total riders 2.4 to 2.8 million Revenue 39
    -42 mill
  • Greeneway route
  • Total riders 3.8 to 4.1 million Revenue 54-
    56 mill
  • Both proposing teams committed to covering
    Operations Maintenance costs based on inclusion
    of the Choice and Captive markets

12
DBOMF SUBMITTALS
  • FLUOR-BOMBARDIER
  • Jet-Train Technology Gas Turbine
  • Double track Disney to OIA, single track to Tampa
  • Firm Fixed price of 2.056 Billion
  • GLOBAL RAIL CONSORTIUM
  • Electric TGV Technology
  • Double track entire system
  • Firm Fixed price of 2.4 Billion
  • F-B was ranked first on 6-2 vote
  • Negotiations proceeded until August 2004

13
ORLANDO MIAMI FEASIBILITY 2004
14
Orlando-Miami Feasibility FHSRA 2002
  • Key Findings for Tampa-Orlando-Miami
  • Operating Ratios (2020)
  • Will revenues from system cover OM costs?
  • For 180mph Operating Revenue 531 mill
  • OM Costs 174 mill RATIO 3.05
  • Benefit-Cost Ratios (30 year NPV)
  • Do Benefits to Society for building this system
    justify the costs?
  • For 180mph RATIO 1.95
  • Conclusion
  • Overall benefits of this system greatly exceed
    costs

15
APPROACH TO RESPONSE
  • Highlights of Proposed Response
  • Corridor Tampa-Orlando-Miami
  • P3 Approach
  • Green Technology
  • Includes Stimulus component shovel ready
    CREATES JOBS!

16
Corridor Definition
  • Tampa-Orlando-Miami Corridor is logical
  • Much work done on entire corridor
  • Entire corridor is designated by FRA
  • Phasing to logical intermediate stations
  • Provides 180 mph capability
  • Reasonable total length (310 miles) compared to
    other competing corridors
  • LA - San Francisco is almost 400 miles
  • Boston - DC is 440 miles

17
Public Private Partnership
  • Private partner is critical for success
  • Leases system for long term
  • Shares profits in excess of defined thresholds
  • A single system approach is logical
  • Single technology
  • One set of standards that is interoperable
    statewide
  • WILL REQUIRE ASSUMPTION OF OM RISK BY PRIVATE
    PARTNER

18
GREEN TECHNOLOGY ELECTRICALLY DRIVEN SYSTEM
  • State of the Art examples
  • Siemens Velaro Alstom AGV

19
Stimulus Approach
  • Sequence of work
  • Define Minimum Operating Segment (MOS) with FRA
    within the Tampa-Orlando corridor
  • Obtain Record of Decision for MOS
  • Start construction of MOS
  • Incrementally add segments on
  • Continue environmental work on next segments
  • GOAL MOS can start construction in 18 months

20
Board Meeting of April 2
  • FDOT Letter of Assistance
  • Offered to take over the application process for
    stimulus funds to use in-house resources
  • FHSRA accepted offer, with three requests
  • 4 million federal funds available to FHSRA from
    4 years ago - FDOT to report status in 2 weeks
  • FDOT to provide progress report at future
    meetings
  • FHSRA requested that institutional memory
    available be used
  • Sunrail FHSRA passed a support resolution 4-1

21
Florida High Speed Rail Authority Update
forOrange County Board of County Commissioners
  • April 7, 2009
Write a Comment
User Comments (0)
About PowerShow.com