Title: Liam Newcombe BCS Data Centre Specialist Group Secretary
1Liam NewcombeBCS Data Centre Specialist Group
Secretary
- Energy Efficient Data Centres
2Cardiff University
Energy Use in the Data Centre EU Code of Conduct
for Data Centre Operators
3Cardiff University
Asking the Wrong Questions Per Service Energy
Use The DCSG Model
4Cardiff University
Asking the Wrong Questions
5The Power Delivery Path
6Cardiff University
For each Watt my Data Centre consumes what
output do I get? vs. For each Service I deliver
how much energy do I use?
7(No Transcript)
8Cardiff University
What is the marginal economic or environmental
benefit of operating this IT service?
9Cardiff University
Per Service Energy Use Data Centres Servers Server
in a Data Centre
10Cardiff University
- Data Centre Power - Where does it go?
11Cardiff University
Per Service Energy Use Data Centres Servers Server
in a Data Centre
12Cardiff University
- Server Power and Efficiency vs. Workload
13Cardiff University
Per Service Energy Use Data Centres Servers Server
in a Data Centre
14Cardiff University
- Put the Server in a Data Centre
- What does DCiE / PUE tell us?
15Cardiff University
Metering Install Detailed Power Metering? What
about Blade Servers and Virtualisation?
16Install Detailed Power Metering?
17Cardiff University
Metering Install Detailed Power Metering? What
about Blade Servers and Virtualisation?
18Metering Fails for Blades or Virtualisation
19Where to Measure
20Cardiff University
Metering Must be able to link logical to
physical Cannot solve our problem
21Cardiff University
DCSG Data Centre Model
22DCSG Data Centre Model
IT Device Load to Power Function
Data Centre Power Transfer Function
23Cardiff University
EU Code of Conduct for Data Centre Operators
24Cardiff University
Context Goals and Scope Development Best
Practice Release
25Cardiff University
Context for the CoC
26Cardiff University
- Political Context
- Carbon reduction commitment
- Energy security
- Industry Context
- Many activities within Industry
- Risk of Confusion and Mixed Messaging
27Cardiff University
- Economic Context
- Rising energy costs
- Data Centres represent an increasing proportion
of overall business cost - Social Context
- Rising public awareness
- Data Centres represent an easy target
- ICT can reduce environmental impact
- Demonstrate that our industry is not profligate
with energy
28Cardiff University
Goals and Scope of the CoC
29Cardiff University
- Goals
- Led by Paolo Bertoldi, Directorate General
- aim is to inform and stimulate Data Centre
operators to reduce energy consumption in a cost
effective manner without hampering the critical
function . - A Voluntary Commitment
- Reward best practice with branding and associated
EU Green marketing.
30Cardiff University
- Scope
- The Code of Conduct covers
- Data centres of all sizes server rooms to
dedicated buildings - Both existing and new
- IT power and Facility power
- Equipment procurement and system design
31Cardiff University
- Scope
- The Code of Conduct is for
- Participants Data centre owners and operators
- Endorsers Vendors, consultants, industry
associations
32Cardiff University
Development
33Cardiff University
- Substantial Interest
- Broad Participation and Support from
- Vendors
- Data Centre Operators
- End User Organisations
- Will become a Supplier Selection Criterion
34Cardiff University
- Working Groups
- Best Practice
- Focused on design best practice, Software, IT
Architecture and Facility - Metrics Measurement
- Developing a standard method of comparative
measurement of energy efficiency - Data Collection Analysis
- Performance benchmarking across the industry
35Cardiff University
Best Practice
36Cardiff University
- Best Practice Intent
- Neither a prescriptive nor exhaustive list of
specific technologies - Focus on goals
- Structured to allow the addition of new
technologies
37Cardiff University
- Best Practice Intent
- Some Practices are required for Participants
- Practices that apply to
- Existing estate
- New IT equipment
- New or refitted Data Centres
- It is understood that not all operators will be
able to implement all required practices
38Cardiff University
- Value of Practices
- Best Practices are guidance to operators on how
they might improve energy efficiency - Practices are scored 1-5 (min-max) based upon
their likely energy use benefit - Practices are ordered by score
39Cardiff University
- Required Practices
- Grid and Virtualisation
- Processes should be put in place to require
senior business approval for any new service that
requires dedicated hardware and will not run on a
resource sharing grid or virtualised platform - Select efficient software
- Make the performance of the software, in terms
of the power draw of the hardware required to
meet performance and availability targets a
primary selection factor
40Cardiff University
- Required Practices
- New IT Equipment
- Include the Performance per Watt of the IT
device as a high priority decision factor in the
tender process - Power Provisioning
- Provision power and cooling only to the
as-configured power draw capability of the
equipment, not the PSU or nameplate rating
41Cardiff University
Example Scenario
- Same Computing Workload
- 100 One App Per Server Servers
- 15 Virtualised Servers
- 10 HPC Grid Servers
- Old N1 Data Centre, Nameplate Provisioning
42Cardiff University
- Old N1 Data Centre, Nameplate
43Cardiff University
- Old N1 Data Centre, Nameplate
44Cardiff University
- Old N1 Data Centre, Nameplate
45Cardiff University
Example Scenario
- Same Computing Workload
- 100 One App Per Server Servers
- 15 Virtualised Servers
- 10 HPC Grid Servers
- Old N1 Data Centre, Peak Provisioning
46Cardiff University
47Cardiff University
48Cardiff University
- Required Practices
- Cooling
- Review and if possible raise target IT equipment
intake air temperature - Above the dew point
- Review of cooling before IT equipment changes
- Rack air flow management
49Cardiff University
- Required Practices Retrofit or New
- Cooling
- Design Contained hot or cold air
- Variable Speed Air Fans
- Rack air flow management
- Utilisation, Management and Planning
- Lean provisioning of power and cooling for 18
months worth of data floor capacity
50Cardiff University
Example Scenario
- Same Computing Workload
- 100 One App Per Server Servers
- 15 Virtualised Servers
- 10 HPC Grid Servers
- New N1 Data Centre, Free Cooling
51Cardiff University
- New N1 Data Centre, Free Cooling 19C
52Cardiff University
- New N1 Data Centre, Free Cooling 25C
53Cardiff University
- New N1 Data Centre, Free Cooling 25C
54Cardiff University
- New N1 Data Centre, Free Cooling 25C
55Cardiff University
Example Scenario
- 15 Virtualised Servers
- Old N1 Data Centre, Nameplate Provisioning
- Old N1 Data Centre, Peak Provisioning
- New N1 Data Centre, Free Cooling
56Cardiff University
- Comparison of Virtualised Scenarios
57Cardiff University
- Comparison of Virtualised Scenarios
58Cardiff University
- Required Practices Retrofit or New
- Cooling
- Design Contained hot or cold air
- Variable Speed Air Fans
- Rack air flow management
- Utilisation, Management and Planning
- Lean provisioning of power and cooling for 18
months worth of data floor capacity
59Cardiff University
CoC Release
60Cardiff University
- Release Target
- Draft released 30th April
- 1st Release September 2008
61Cardiff University
Thank you Find out more Data Centre Specialist