Title: The Hong Kong Institute of Surveyors Construction Law Update
1The Hong Kong Institute of SurveyorsConstruction
Law Update
- Damon So and Timothy Hill
- Projects (Engineering and Construction) Group
- 28 August 2007
2Breach without loss?Closing the legal black
hole
- Damon So, Senior Associate
- Projects (Engineering and Construction) Group
3The Legal Black Hole
property
Employer
Subsequent Owner
privity of contract
Loss suffered as a result of breaches by
consultants
Consultants/ Contractors
4The Tortious Claim
Employer
Subsequent Owner
tort
Consultants/ Contractors
5The Tortious Claim (Contd)
- Problems
- Pure economic loss
- - recoverable if personal injury or other
property damage involved - loss incurred to prevent personal injury or
property damage - cost of repair and damage to property concerned
- special relationship/assumption of duty
6The Contractual Claim
assignment of cause of action
Subsequent Owner
Employer
incurred loss
contractual cause of action
Consultants/ Contractors
7The Contractual Claim (Contd)
- Problems
- Assignment of cause of action
- assignee cannot recover more than assignor
- Employer only suffered nominal damages
- no cause of action for substantial loss
- assign no more than it is entitled to
- assignee only entitled to recover nominal
damages
8The Legal Black Hole
Linden Gardens Trust v Lenesta Sludge Disposal HL
1993 3 All ER 417
If this is right, in the words of Lord Keith of
Kinkel in GUS Property Management Ltd v
Littlewoods Mail Order Stores Ltd 1982 SC (HL)
157 at 177, the claim to damages would disappear
into some legal black hole, so that the
wrongdoer escaped scot-free.
9The Courts intervention
- In the Linden Gardens case
Assignment invalid
Subsequent Owner
Original Owner
Substantial damages for subsequent owner
Contractors
- General rule
- a plaintiff can only recover substantial damages
for its own loss - a plaintiff who had parted with ownership of
property at the date of the breach was not
entitled to damages or was entitled to nominal
damages at most.
10The Courts intervention (Contd)
Exception to the general rule Original owner can
recover substantial damages for the subsequent
owner if
- contract entered into on the footing that the
original owner would be entitled to enforce
contractual rights for the benefit of those who
suffered from defective performance, but - the third party could not acquire any right to
hold the defendant liable for breach
11Legislative intervention in the UK
- Contract (Rights of Third Parties) Act 1999
- reforms privity of contract rule
- third party may in his own right enforce a term
of the contract if - (i) the contract expressly provides that he
may or - (ii) the term purports to confer a benefit on
him. - third party must be expressly identified in the
contract - subject to the terms of the contract
12Rights of assignee
- What if the Act does not apply, as in HK?
- What if there is a valid assignment?
- unnecessary for HL to consider the assignees
remedies in the Linden Gardens case - CA considered the question which HL did not apply
- Technotrade v Larkstore, CA 2006 BLR at 345
13The Facts
- November 1998 - Starglade retained Technotrade to
prepare a site investigation report in relation
to a sloping site (the Site) - December 1998 - Technotrade produced their Site
Investigation Report (the Report) - June 1999 - Starglade sold the Site to Larkstore
- March 2001 - Larkstore had used the Report for
design and construction and for obtaining
planning permission
14The Facts (Contd)
- October 2001 - landslip occurred causing damage
to properties uphill from the Site and
necessitating stabilisation works to the Site - February 2004 - Starglade assigned rights under
the Report to Larkstore - October 2004 - Larkstore commenced proceedings
against Technotrade based upon the assignment
15Three relevant points of time
- Time of breach
- - Site Investigation Report
- - Starglade was owner
- - only nominal damages
- Time of the landslip
- - Larkstore was owner
- - substantial damage suffered
- - no contractual right
-
16Three relevant points of time (Contd)
- - Starglade had chose in action, but not entitled
to substantial damages not being the owner - 3. Time of the assignment
- - Starglade could not assign more than it had
- - no claim for substantial damages could be
assigned
17Timing of relevant events
(ii) sold property
Starglade
Larkstore
- assignment of rights after landslip
- Site
- Investigation
- Report
- Loss suffered due to landslip stabilisation work
required
Technotrade
18What was assigned?
- Cause of action
- complete at time of breach
- nominal damages?
- Staughton LJ in Linden Gardens
- the assignee can recover no more damages than
the assignor could have recovered if there had
been no assignment, and if the building had not
been transferred to the assignee.
19What was assigned? (Contd)
- - remedy in damages not limited to the loss that
could have been proved at the time of breach - includes loss which occurs after the cause of
action has accrued - - assignment of cause of action remedies, not
a loss
20The Principle
- the assignee cannot recover more than the
assignor - at the date of assignment, assignor only entitled
to claim nominal damages - purpose of the principle protect
contract-breaker from paying more damages to
assignee than to assignor had the assignment
never taken place - not intended to enable contract-breaker to escape
all legal liability creating the legal black
hole
21No legal black hole
- parties did not contemplate anyone other than
Starglade would suffer loss - Technotrades retainer based on Starglade
carrying out the development - Larkstore did not seek any warranty from
Technotrade - Larkstore did not engage its own geotechnical
advisers and relied on Technotrades report
without consent for a purpose not intended
22The Court
- an ingenious attempt to deny what has been
correctly conceded - the Report and causes of action were assignable
- no prohibition against assignment
- arguments rejected
23Position in Hong Kong
- Linfield v Taoho and Ors, 3 September 2004
- - arrived at the same results through different
routes
property
Sing Kee
Linfield
assignment
GWA
24The Tort route
- Linfield is a wholly owned subsidiary of Sing Kee
- GWA treated them interchangeably, e.g. payments,
correspondence - assumption of special relationship
- Hedley Byrne principles apply
- pure economic loss recoverable
25The Contract route
- Panatown v Alfred McAlpine Construction 2000 4
All ER 97 - right to performance interest, being the cost
to Sing Kee of providing the agreed services to
Linfield, the broader ground - could have applied the exception in the Linden
Gardens case, the narrower ground - this right could be assigned
26Expert Determination
- Timothy Hill, Managing Partner
- Projects (Engineering and Construction) Group
27Specimen Clause General
- Expert shall act as experts and not as
arbitrators and their or his determination shall
be conclusive and final and binding for all
purposes.
28Specimen Clause Share Valuation
- The expression Fair Price means the price
which the auditors of the Company state in
writing to be in their opinion the fair value of
the shares on a sale between a willing seller and
a willing purchaser and, if the Company is then
carrying on business as a going concern, on the
assumption that it will continue to do so. The
Fair Price shall be assessed at the date of
service of the Transfer Notice and by reference
to the information available to the company at
that date. - In stating the Fair Price the auditors shall be
considered to be acting as experts and not as
arbitrators and their decision shall be final and
binding on the parties.
29Expert or Arbitrator?
30The Process
- Agreement
- Submissions
- Reference to others
- Investigation
- Co-operation
- Third Parties
31The Decision
- We determine the sales amount to 2,527,135
- Jones v Sherwood Computer Services plc
32Halifax Life Ltd v Equitable Life
33Challenge to Decision
- No right to challenge
- Exceptions
- Does not comply with mandatory requirement
- Answers wrong question
- Fraud or collusion
34Enforcement
- No streamline procedure
- - New York Convention
- Enforce as a breach of the underlying contract
- - Nature of decision
- - Strict compliance required
- - Limitation period
35Court Proceedings
- Stay of proceedings
- Contracts void ab initio
- Where mechanism breaks down
36Position of Experts
- No immunity from suit
- Contractual agreement to appoint
- Liability for negligence
37Advantages of Expert Determination
- Quick
- Informal procedure
- Absence of formal presentations
- Cheap
- Knowledge base
- Private
38Disadvantages of Expert Determination
- No right to interest
- No right to costs
- No provision to compel
- - Disclosure of documents/information
- - Co-operation of witnesses
- No right of appeal
- Enforcement
39Questions?
40Expert Determination
- Timothy Hill, Managing Partner
- Projects (Engineering and Construction) Group
41The Hong Kong Institute of SurveyorsConstruction
Law Update
- Damon So and Timothy Hill
- Projects (Engineering and Construction) Group
- 28 August 2007