Title: Caernarvon Update


1
Caernarvon Update
Louisiana Department of Natural
Resources Coastal Restoration Division CPRA
2008 Chuck Villarrubia
2
Caernarvon Operations Response to Hurricane
Katrina
  • Term 1/06-present
  • Response to marsh loss from Katrina
  • From Dec-June up to 8,000 cfs pulses
  • Attempt to increase footprint of diversion, catch
    sediment peaks in river

3
Mean5,400 cfs 5.5 million acre-feet
4
(No Transcript)
5
(No Transcript)
6
Modification to Caernarvon
  • In 2005, mostly as a result of Hurricanes Katrina
    and Rita, the Breton Sound Basin lost 40 Miles2
    of marsh in addition to the 67 miles2 lost
    between 1956 and 2004
  • Congressionally directed by Public Law
    109-234,Title II on June 8, 2006
  • authorized 10,100,000 to reduce the risk of
    storm damage to the Greater New Orleans
    metropolitan area, at full federal expense, by
    restoring the surrounding wetlands through
    measures to begin to reverse wetland losses in
    areas affected by navigation, oil and gas, and
    other channels and through modifications of the
    Caernarvon Freshwater Diversion structure or its
    operations.

7
  • Study Goal
  • Construct a storm damage reduction measure that
    will complement the comprehensive hurricane
    protection and ecosystem restoration goal for
    southeastern Louisiana by restoring coastal
    wetlands
  • Maintain Integrity of Original Caernarvon
    Freshwater Diversion Project
  • Planning Constraints
  • Limited Budget
  • Environmental alternatives must compliment not
    hinder purpose of Caernarvon Freshwater
    Diversion Project

8
Proposed Alternatives
  • The change in the original project structures
    operation schedule for maximized wetland
    restoration (e.g., sediment delivery to adjacent
    wetland)
  • Restoration of Plugged Canals and Construction
    of Breaches to allow diverted water to reach
    interior marsh areas
  • Marsh creation in selected areas via sediment
    delivery either through pipeline or direct dredge
    and fill activities
  • Closing the shoreline breaches along Lake Leary
    to retain diverted sediments within wetland
    areas.

9
Areas of Consideration
Diversion Structure
MC
Braithwaite Canal
Delacroix Canal
10
Project Status
  • Hydrologic Modeling Withdrawn November 2007
  • Value Engineering Efforts November 2007
  • General Exploratory Investigations (Surveys)
    Feb. 2008
  • Soil Testing Investigations (Borings) March
    2008
  • Environmental Site Assessment April 2008
  • Draft Project Description Document July 2008
  • Anticipated Construction Mid 2009

Assuming no Higher Command concerns and/or no
Real Estate Delays
11
(No Transcript)
12
(No Transcript)
13
Caernarvon Structure Facts
  • Flood Control Act 1965 and WRDA 1974
  • Constructed by USACE, operated by LDNR
  • Online in 1991
  • 5-15 ft2 box culverts
  • Discharge 8,000 cfs
  • Operational oversight by CIAC
  • Cost 26.1 million
  • 16,000 acres preserved
  • 77,000 acres benefited

14
(No Transcript)