A - PowerPoint PPT Presentation

About This Presentation
Title:

A

Description:

... the Revenue Gap through increase in tariff, reduction in BST, Govt. ... Rebate _at_ 2% for payment of BST bills within three working days from the date of ... – PowerPoint PPT presentation

Number of Views:33
Avg rating:3.0/5.0
Slides: 41
Provided by: DIRECT3
Learn more at: https://www.orierc.org
Category:
Tags: bst

less

Transcript and Presenter's Notes

Title: A


1
ORISSA ELECTRICITY REGULATORY COMMISSION
Together, let us light up our lives.
A Presentation on ARR Tariff Proposal of
SOUTHCO for FY 2007-08 Broad Suggestions/Objecti
ons Feburary 9, 2007
2
Data Sources
  • As stated by SOUTHCO
  • The Accounts up to September 2005 have been
    audited as per Companies Act
  • The accounts up to March 2006 have been audited
    as per Income Tax Rules
  • It has relied upon the audited accounts upto
    September 2005 as per Companies Act and accounts
    upto March 2006 as per Tax Audit for preparation
    of ARR

3
(No Transcript)
4
(No Transcript)
5
Tariff Structure
  • SOUTHCO has proposed
  • No change in tariff structure
  • No special tariff should be allowed to the
    industries having own CPPs
  • Demand charge of Rs 200/- per KVA to be
    applicable for consumers having contract demand
    70 KVA and above under HT Industrial (M) and GP
    category
  • The provisions of tariff applicable to large
    industries should be made applicable to above
    consumers.
  • Fixed charges for LT Industrial(S), LT
    Industrial(M) PWW to be levied on KVA in place
    of KW.
  • Demand charges _at_ 120 of demand charges to be
    made applicable on MD recorded along with
    applicable energy charges for CPPs

6
Tariff Structure .. Contd..
  • The minimum demand charges concept i.e. 80 of
    CD should not be made applicable to CPPs
  • Service connection charges for single phase
    Domestic / GP consumers upto 3 KW load to be
    revised from Rs 500/- to Rs. 1000/-.
  • The rate of labour component to be taken by the
    consumers equivalent to Rs. 400/-where single
    phase consumers come forward and provide service
    connection materials.
  • Monthly minimum fixed charges for consumers with
    contact demand lt 100 KVA should be levied on CD
    or MD whichever higher

7
Tariff Structure .. Contd..
  • Tariff for medium industries (LT) may be
    considered at par with GP (LT)category.
  • The over drawl energy should be considered in
    cumulative basis for all DISTCOs together instead
    of considering DISTCO wise over drawl till to
    Intra-State ABT is implemented.
  • Rebate _at_ 2 for payment of BST bills within three
    working days from the date of presentation of
    bill.
  • Delayed Payment Surcharge to be levied to LT
    industrial (Small) supply category.
  • Bridge the Revenue Gap through combination of
    increase in Retail Supply Tariff, Reduction in
    Bulk supply Tariff, Government Subsidy etc.

8
Reconnection Charges
9
BROAD TARIFF RELATED ISSUES RAISED BY OBJECTORS (
To be addressed by the Licensees )
10
Legal Issues
  • The ARR application filed by the licensee is not
    tenable under law due to the following defects
  • The licensees account has not been audited for FY
    2004-05 and 2005-06.
  • The licensee has filed the application to confuse
    the consumer public without disclosing the
    purpose for such filing.
  • The interested persons are being kept in dark and
    not able to file effective objection and as such
    the purpose of such exercise has been frustrated
    and contrary to law and principle of natural
    justice.
  • The procedure/method so adopted by the Commission
    be made simple and inexpensive.
  • The licensee has failed to provide details as
    required under regulations to the Commission for
    consideration of his application as such the
    application may be rejected.

11
Issues raised by Objectors
  • Military Engineering Services
  • There should be discriminatory Tariff between
    consumers of general category and of the defence.
  • Distribution Loss
  • The licensee has miserably failed to arrest high
    Distribution loss on account of unauthorized use
    of power.
  • Distribution loss should be calculated by taking
    ratio of units lost in distribution system
    excluding EHT sale.
  • Since, a large chunk of consumers are still
    unmetered and having defective meters, the
    declared loss by the licensee is unrealistic.
  • Collection Efficiency
  • The consumers are not to be burdened for
    in-efficiency of licensees to collect their
    energy dues from consumers every year.

12
Issues raised by Objectors.. Contd..
  • ATC Loss
  • ATC concept should not be implemented as it
    hides the inefficiency of the Licensee.
  • Power Factor Incentive/ Power Factor Penalty
  • Power Factor incentive has to be calculated upto
    two decimal fraction
  • Power factor penalty is levied for power factor
    less than 90 power factor incentive should be
    given for power factors above 90 at the same
    rate.
  • Power factor penalty for the small and medium
    industry consumer may be introduced.
  • Cross Subsidy
  • Bench Marks for gradual reduction of cross
    subsidy may be fixed from this year to achieve
    Zero level by 2009-10.

13
Issues raised by Objectors.. Contd..
  • Quality of Services
  • The industries are put to financial burden for
    being unable to achieve 80 Load Factor due to
    the inability of the licensee to supply proper
    quality power.
  • Due to slow up gradation of the system and
    sub-station, the new industries are finding
    difficult to get power connection.
  • Voltage/frequency fluctuation The accountability
    should be fixed with the License in terms of
    financial compensation for the fluctuation beyond
    standard norms.

14
Issues raised by Objectors.. Contd..
  • Consumer Classification
  • Electricity tariff for poultry may be at par with
    agriculture.
  • The State Government has decided to classify
    poultry as agriculture
  • Reliance Telecom Ltd. and Reliance Infocomm Ltd.
    - Electricity energy may be charged at
    Industrial Rates instead of General Purpose
    rates to the IT ITES Industries operating in
    the State
  • BSNL Orissa Circle, Bhubaneswar
  • BSNL may be treated as an industrial undertaking
    as power is substantially utilized as motive
    force for Industrial purpose and without supply
    of power it is not possible to run the Telecom
    services.
  • The BSNL is coming under the purview of industry
    as per the verdict of the Honble Supreme Court
    in several cases.
  • So also as per the finance Act, 2002 w.e.f.
    01.4.03, the business of providing
    Telecommunication Services has been declared as
    industrial undertaking.

15
Issues raised by Objectors.. Contd..
  • Financial Issues
  • In absence of the audited balance sheet and
    report of the auditors it is not possible for the
    objector to make proper observation on financial
    matters.
  • Interests attributable to bonds
  • The interest attributed to bonds against arrear
    of power purchases cost and capital value of
    bonds are not payable by consumers.

16
Issues raised by Objectors.. Contd..
  • Interests towards securitization
  • The interest towards securitization as well as
    capital of securitization should not be passed on
    to the revenue requirement for tariff proposes.
  • Infusing additional funds - The licensee may be
    directed to infuse additional funds as may be
    required to turn around the sector.
  • Regulatory assets - Any losses that the
    distribution licensee likes to incur after
    complying with the orders of the Commission, can
    only be considered for the purpose of computing
    the Regulatory Assets.
  • Employees cost - It is suggested that an increase
    of about 6 over last years provision may be
    allowed while fixing the employees cost for the
    FY 2007-08.
  • Past Losses - Past losses should be paid through
    tariff by consumers only if these losses have
    been incurred due to reasons beyond the control
    of licensee and in spite of licensee having
    performed as per bench marks fixed by OERC.

17
Issues raised by Objectors.. Contd..
  • Computation of Load Factor
  • Load factor or consumption ratio to be determined
    on the basis of Maximum Demand recorded in the
    meter in accordance with Regulation 2(y) of the
    OERC Distribution (Conditions of Supply) Code,
    2004.
  • It will be just and proper to calculate the load
    factor on the basis of Maximum Demand or 80 of
    the Contract Demand whichever is higher.
  • A lower load factor upto 50 may be prescribed
    for the period of annual maintenance, which will
    be jointly decided by the licensee and the
    consumer.
  • The guaranteed load factor of 80 should be
    determined on an annual basis.
  • Load factor may be computed separately for peak
    and off peak hours and the overall load factor be
    computed by integrating the above data.
  • The LF be calculated based on the actual period
    of availability of unrestricted power supply
    during the month.
  • The MD during the off peak hours should not be
    considered for computing the LF.

18
Issues raised by Objectors.. Contd..
  • Tariff Issues
  • The gap of electricity charges between high
    consumption and low consumption should be reduced
    to minimum level, which will discourage theft of
    energy.
  • Contract Demand
  • Time frame for reducing the contract demand may
    not be imposed.
  • Provision for Rebate
  • Seven clear days may be given from the receipt of
    the bill to get the rebate on prompt payment.

19
Issues raised by Objectors.. Contd..
  • Emergency Supply to CPPs
  • The proposal of demand charges for emergency
    drawal to CPPs should be rejected.
  • Emergency power requirement for CPP/Generating
    stations are very low and for short duration
    only, it is not at all justified to propose
    demand charges for emergency power to CPPs.
  • Rail-ways
  • Adoption of single part tariff for Railway
    traction.
  • Proper adoption of simultaneous maximum demand
    for Railway traction supply.
  • Railway may be exempted from payment of Security
    deposit.
  • Stipulation of penalty on power factor if it goes
    below 0.85 as against 0.90.
  • Stipulation of incentive for improvement in power
    factor above 0.85.

20
Issues raised by Objectors.. Contd..
  • Grant of relief to railways for power supply
    interruption as well as poor quality of supply.
  • The tariff applicable to Railway Traction should
    reflect the cost of supply without any cross
    subsidy.
  • As far as supply to Railway Traction Sub-station
    is concerned, the distribution companies are not
    entitled to any wheeling charges as non of their
    own asset is involved in the supply process.
  • Ignoring of maximum demand of TSSs during feed
    extensions as Railways are constrained to extend
    feed from adjacent TSS to the failed TSS zone.
  • The tariff clause for industrial colony
    consumption should be applicable to Railway
    colony.

21
Issues raised by Objectors.. Contd..
  • General Issues
  • The additional costs actual or estimated on
    account of the inefficiency/inability of licensee
    should not be passed on to the consumers through
    the tariff, either as a direct cost or a so
    called Regulatory Asset.
  • Any cost due to additional power purchase, beyond
    the allowable distribution loss should not be
    included in the ARR of the licensee.
  • Increase in the reconnection charge no
    justification.
  • The charges to the consumers should reflect the
    cost to the licensee.
  • DPS for LT consumers no justification.
  • A LT consumer loses the rebate of 10 p/kwh in a
    month. Additional levy of DPS is thus unnecessary
    and un reasonable.

22
Issues raised by Objectors.. Contd..
  • The demand charges may be calculated prorate if
    the total of period of interruption (causing loss
    of production due to interruptions) and the
    pre-arranged shut downs availed on intimation, or
    statutory power cuts, exceeds 60 hours in a moth.
  • The street light burning hours should be on
    actual time i.e. for 10 hours a day.
  • The ceiling limit of 10 of total consumption for
    the colony consumption should be waived
  • Electricity charges for the colony consumption
    should be at per with domestic rate because the
    electricity used in the colony is never used for
    any industrial purpose.
  • Special tariff for running of FOUNDRY A special
    tariff structure _at_50 of the existing tariff, may
    be introduced for running of the furnaces.

23
Issues raised by Objectors.. Contd..
  • Demand charges
  • The demand charges may be calculated on prorate
    basis for the actual period of power
    availability.
  • The demand charges may be exempted if there is
    power interruption for more than 50 hours in a
    month.
  • To have a uniform tariff for all consumers based
    on commercial principle of cost plus benefit
    basis.
  • Separate Tariff may be introduced for Specified
    Public Purpose consumers under private sector
    especially for Educational Institutions.

24
Issues raised by Objectors.. Contd..
  • Service Connection charges - It is suggested that
    a realistic amount in place of Rs500/- may be
    fixed so that the Licensee can procure quality
    materials in time.
  • Uniform rate may be introduced for LT (domestic)
    without any slab system.
  • Tariff Revision - The proposed tariff revision is
    not at all desirable as there is no improvement
    in services.

25
Issues raised by Objectors.. Contd..
  • OERC Regulations
  • During the initial period of supply, which is
    prescribed for five years, an Exit Clause should
    be provided since the consumer has right to
    choose its supplier.
  • Customers Security Deposit Consumers may be
    permitted to furnish bank guarantee or to open
    revolving letter of credit in favour of licensee
    in lieu of security deposit as it becomes
    extremely difficult for small and medium scale
    industry to invest such huge sum for purchase of
    power in cash.
  • Period of agreement The validity of power
    agreement is presently 5 years, should be reduced
    to 1 year in view of the changing market scenario
    and fluctuating market demands.

26
BROAD TARIFF RELATED ISSUES
27
The following areas have not been adequately
addressed
  • D.T. wise Energy Audit Consumer Indexing for
    loss reduction
  • Spot Billing Collection for improvement of
    Collection Efficiency
  • Repair Maintenance
  • Arrear Collection Liquidation of power purchase
    dues
  • Man power deployment ( Both Executive Non
    Executive ) for reducing AT C Loss
  • Non Investment in system improvement for Quality
    Supply

28
(No Transcript)
29
Revenue Requirement for 2007-08 ..Contd..
  • Bifurcation of the amount towards cost of power
    purchase and cost of transmission for FY 2007-08
    has not been furnished. The same may be
    submitted.
  • Actual expenditure against the above heads of
    expenditure for first six months of FY 2006-07
    has not been provided by the licensee. The same
    may be submitted.
  • The reason for making higher provision in
    employee cost of Rs.98.23 crore proposed for FY
    2007-08 as against the approved amount of
    Rs.68.18 crore for FY 2006-07 and Rs.61.22 crore
    appeared in the tax audit report needs to be
    justified.
  • The proposed rise in AG expenses for an amount
    of Rs 20.72 crore for FY 2007-08 as against the
    approved amount of Rs 10.88 crore for FY 2006-07
    and Rs. 13.62 crore for the FY 2005-06 based on
    Tax Audit reports needs to be explained.
  • Similarly, the quantum proposed for interest
    amounting Rs.46.73 crore for FY 2007-08 is nearly
    Rs.20 crore more than the approved amount of
    Rs.26.77 crore for FY 2006-07 and nearly Rs. 25
    crore more than the tax audited figure for the FY
    2005-06. This needs to be explained.
  • It may be justified as to why the amortization of
    regulatory asset and truing up of revenue gap
    for the FY 2006-07 be allowed and if so how far
    it is reasonable.

30
RM Expenses of SOUTHCO (Rs. Cr.)
Note (i) Cause of declining expenditure in RM
?? (ii) Non utilisation of the approved amount
towards RM is affecting Quality of Supply
increasing interruption.
31
Note Why the Gap Between the approved and actual
figures of various heads of expenditures have not
been adjusted in the Revenue Requirement filing ?
32
Provision for Bad Doubtful Debt
33
Miscellaneous Income SMD
  • Miscellaneous Income
  • At the time of determination of RST for 2006-07
    for the purpose of computation of misc. income
    the latest available audited data for FY 2003-04
    was taken into consideration. Now, that audited
    accounts for FY 2004-05 and accounts upto March
    2006 as per tax audit are available and even
    after deduction of DPS from the misc. income for
    FY 2004-05 as per audited account is much higher
    than what has been approved for 2006-07.
  • Determination of Simultaneous Maximum Demand
    (SMD)
  • Whether increase/decrease in energy consumption
    has got direct link with SMD.
  • Comments on the above subjects are invited for
    determination of tariff.

34
Business Plan Vrs. ARR
  • A comparison of figures in Business Plan and ARR
    from FY 2004-05 to 2007-08 with regard to
    Distribution Loss, Collection Efficiency and ATC
    Loss, present two different sets of figures with
    wide margins as follows

35
SOUTHCO ARR FILING VRS BUSINESS PLAN
36
Finance related issues
  • Investment details have not been specified.
  • Capital Works In Progress - capability of huge
    investment proposal has not been justified.
  • Action plan for settlement and collection of
    arrears outstanding with the consumers have not
    been spelt out.
  • No Action Plan for establishment of Special
    Police Station Special Court has been given

37
Issue of Regulatory Assets
  • National Tariff Policy on Regulatory Assets
    stipulates
  • Pass through of past losses or profits should be
    allowed to the extent caused by uncontrollable
    factors.
  • The facility of a regulatory asset should be done
    only as exception, and subject to the following
    guidelines.
  • should only include natural causes or force
    majeure conditions
  • Carrying cost of Regulatory Asset should be
    allowed to the utilities
  • Recovery of Regulatory Asset should be time-bound
    and within a period not exceeding three years at
    the most and preferably within control period.
  • The use of the facility of Regulatory asset
    should not be repetitive.
  • Does the claim of Licensee conform to the
    National Tariff Policy?
  • Whether the past losses be treated as regulatory
    asset and allowed in tariff along with carrying
    charges?
  • Whether the interest cost an account of the
    regulatory asset should be allowed to be
    recovered as a pass through

38
Average Revenue Billed (P/U) Vrs Actual as filed
by SOUTHCO in ARR filings
39
(No Transcript)
40
Thank You
Write a Comment
User Comments (0)
About PowerShow.com