Title: World Bank Experience: Road Asset Management and Development through Public-Private Partnerships Cesar Queiroz Highway Advisor World Bank Kyiv, March 21, 2006
1World Bank Experience Road Asset Management and
Development through Public-Private
PartnershipsCesar QueirozHighway AdvisorWorld
BankKyiv, March 21, 2006
First International Conference Perspectives for
Ukraine on Implementation of Public-Private
Partnerships
2Outline
- Brief International Overview
- Lessons Learned from Past Transport PPPs
- How Can the World Bank Group Support PPP
Development - Selection of the Strategic Investor
- World Bank Toolkit for PPP in Highways
- Allocation of Risks and Payment Mechanisms (e.g.,
availability fees, shadow tolls, BOT, BOO) - Estimating Minimum Toll Rates to Attract Private
Investors - The Way Forward
3PPPs are becoming a global business however
reaching financial close remains a challenge
Source Public Works Financing-Major Project
Survey 1995-2004
4PPPs remain concentrated in a select group of
countries
5What Have We Learned?
- Successfully concluding a transport PPP is a
challenge - As a result of unrealistic and aggressive bids, a
large number of projects face re-negotiation - Government commitment can disappear in periods of
financial stress - Historically only 55 of proposed projects have
reached financing
6What Have We Learned?
- Cost recovery is a major challenge
- Full cost recovery is only achievable in some
transport sub-sectors - Revenue projections often suffer from a bias
towards optimism - The vulnerability of PPP projects to changing
political, financial and economic circumstances
is often underestimated - Access to local currency funding is a critical
success factor for infrastructure projects with
local currency revenues
7Selection of the Strategic Investor or
Concessionaire
- For large projects, it is recommended to carry
out - 1. Prequalification
- 2. A Two-Stage Bidding
8Prequalification
-
- Advertising notice requesting expressions of
interest to pre-qualify to be published locally
and internationally - Investor feedbackmeeting with selected potential
investors/ concessionaires - Public informationinformation dissemination on
the financing and construction of the project - Pre-qualificationinclude financial and
operational criteria to ensure bids from only
qualified candidates
9Two-Stage Bidding
The First Stage
Client prepares functional performance
specifications
Bidders offer unpriced technical proposals
Client evaluates technical proposals, and
indicates what bidders should do to make their
bids responsive
The Second Stage
Client sends memorandum of changes for each
bidder and addendum to bid documents, if necessary
Bidders offer amended bids containing their final
technical proposal and a financial proposal
Client evaluates combined technical and financial
proposals
10Unsolicited Proposals to Governments
- Origin of most controversial private
infrastructure projects - In theory, generate beneficial ideas
- In practice, some unfavorable experiences (e.g.,
attempt to avoid competition, exclusive
negotiations behind closed doors) - Usually sole-source negotiations take much longer
than expected
11Should Governments Forbid Unsolicited Proposals?
- Some governments forbid all unsolicited proposals
to reduce public sector corruption and
opportunistic behavior by private companies (e.g.
Colombia) - Some countries require market-testing (e.g.,
Sri Lanka, Australian States) - Some recognize a good project idea in the tender
by compensating the original project proponent
while holding an ICB (e.g., Chile, S. Africa, S.
Korea)
12Incentive Schemes
- How can the government provide incentives
- for private sector firms to participate?
- Cost sharing and pricing arrangements
- Incentive payments (or penalties) linked to
performance standards - Support the provision of guarantees
- (e.g., World Bank Partial Risk Guarantee)
13World Bank Group Instruments Available to Support
PPPs
- The World Bank
- Loans to governments
- Partial credit and partial risk guarantees
- Technical assistance
- International Finance Corporation - IFC
- Loans to the private sector
- Equity investment
- Technical Assistance
- Multilateral Investment Guarantee Agency - MIGA
- Political risk insurance
14Possible Roles of the World Bank
- Financing part of government subsidies to the
construction cost of a project - Providing a Partial Risk Guarantee (PRG) to the
private investors reduced interest rate,
increased maturity
15World Bank Partial Risk Guarantee Structure
Governt
World Bank
Counter Guarantee
World Bank Guarantee
Concession Agreement
Project Company or Concessionaire
Private Lenders
Loan Agreement
16PRG for a Sub-national Project
Counter Guarantee
WB Guarantee
Private Lenders
Federal Government
Buys Guarantee
Legal Framework
Loan Agreement
Provincial Government
Concession
Project SPV
17Coverage of World Bank PRGs
- Cover specific government obligations to a
private project - Guarantee payment against default on private debt
due to non-performance of government contractual
obligations - Relevant when there is a high perceived risk of
policy reversal - Coverage examples
- performance of government or state owned
entities, e.g., government contractual purchase
and supply obligations - political events, e.g., changes in law,
expropriation, nationalization contract
frustration obstruction in arbitration process
non-payment of termination amount or arbitral
award - certain force majeure events
- foreign exchange convertibility/transferability
18Benefits of WB Partial Risk Guarantees for
- Public sector
- Catalyze private financing and facilitate PPP
- Reduce government risk exposure by shifting
commercial risk to the private sector - Encourage larger co-financing
- Private sector
- Reduce risk of private transactions
- Mitigate risks difficult for the private sector
to manage - Open new markets
- Lower the cost of financing and extend maturities
- Improve project sustainability
19Partial Risk Guarantee Facility for Perus
Infrastructure PPP Program
- Facility Size US 200 million Maximum
individual guarantee amount US 50 million - Project Eligibility Criteria
- Projects in the infrastructure sector
- PPP concession (or similar) contracts
- Economically and socially desirable and
technically viable, but financially viable only
with appropriate government support - In compliance with applicable WB safeguard
- Coverage Up to 50 of project debt against
political, regulatory and breach of contract
risks to project lenders - Duration 5 years of government obligations on a
rolling basis for a maximum of 15 years - Currency Local currency or US denominated debt
20Basic Assumptions to Estimate the Minimum Toll
Rate to Attract Private Investors for a PPP
Project
- Concession term 20 yrs
- Construction Cost 1M/km to 5M/km
- Operation cost 500,000/km/yr
- Equity 14
- Subsidies 0
- Interest rate 5/yr
- Grace period 4 yrs
- Repayment period 14 years
- Discount rate 10
- Initial traffic 5,000 vpd to 20,000 vpd
- Traffic growth 3
- Inflation 6
- Tax 18
- IRR 12
- ROE 16
- LLCR 1.0
- DSCR 1.0
21Toolkit for PPP in Highways
- The toolkit is structured under five headings and
includes a library and interactive financial
simulation model
Available on the World Bank web site
www.worldbank.org/highways
22(No Transcript)
23Estimated Minimum Toll Rate to Attract Private
Investment for a PPP Project
/km
5,000 vpd
10,000 vpd
15,000 vpd
20,000 vpd
Construction cost, million/km
24Value Engineering
- A professionally applied, function oriented,
creative and systematic team management approach,
used to analyze and improve value in
transportation projects - Provides a balance of quality, performance and
functionality in a project, minimizing life cycle
costs of construction, operation and maintenance
25Benefits of Public Disclosure of Concession
Agreements
- Further check on corruption, which in addition to
its direct benefits can enhance the legitimacy of
private sector involvement in often sensitive
sectors - Provision of consumers with a clearer sense of
their rights and obligations, and can facilitate
public monitoring of concessionaire performance
26Payment Mechanisms
- Availability Fee is paid to the concessionaire by
the government based on the availability of
required capacity (number of lanes in
satisfactory condition) - Shadow Toll is paid to the concessionaire by the
government, not charged to motorists, on the
basis of veh-km achieved (volume and composition
of traffic) - BOT is a scheme where the government contributes
land to the project and sometimes a negotiated
financial support, while the concessionaire
builds, maintains and operates the motorway and
transfer the assets after the concession
completion. The commercial risk rests with the
concessionaire - BOO is similar to BOT, but does not involve the
transfer of the assets to the government
27Allocation of Risks by Forms of Concession
100
Availability Fee
Shadow Tolls
RISK TO PUBLIC SECTOR
BOT
BOO
Decreasing Public Risks, Increasing Private Risks
0
100
RISK TO PRIVATE SECTOR
28Transport Infrastructure Way Forward in Ukraine
- Developing local currency markets for
contributing to transport infrastructure
development - Learning from lessons of experience from regional
transition economies, e.g., motorways in Hungary,
ports in Poland - Structuring PPPs is a complex, time demanding
exercise that requires dedicated resources from
the public sector consider establishing a
Transport PPP Unit - Selecting a small number of transactions with the
highest potential for success in the short term - Developing a consistent and organized approach to
assess, evaluate and monitor contingent
liabilities arising from public financial support
to PPP transport projects - Developing smart and effective risk mitigation
products for supporting PPPs
29(No Transcript)
30Thank you!
31Some Basic References
-
- World Bank (2001). World Bank-Financed
Procurement Manual Draft. Washington, D.C.
http//siteresources.worldbank.org/PROCUREMENT/Res
ources/pm7-3-01.pdf - Guasch, J. Luis (2004). Granting and
Renegotiating Infrastructure Concessions Doing It
Right. Washington, D.C. World Bank.http//www-wd
s.worldbank.org/servlet/WDSContentServer/WDSP/IB/2
004/05/06/000090341_20040506150118/Rendered/PDF/28
8160PAPER0Granting010renegotiating.pdf - World Bank (2004). Guidelines Procurement
Under IBRD Loans and IDA Credits. (May).
Washington, D.C. http//siteresources.worldbank.or
g/INTPROCUREMENT/Resources/Procurement-May-2004.pd
f - Queiroz, Cesar (2005). Launching Public Private
Partnerships for Highways in Transition
Economies. Transport Paper TP-9. (September).
Washington, D.C. World Bank. -
- Kerf and et al. (1998). Concessions for
Infrastructure A Guide to Their Design and
Award. Technical Paper no. 389. -
- World Bank (1998). Bidding for Private
Concessions. The Use of World Bank Guarantees.
RMC Discussion Paper Series, no 120. Washington,
D.C.
32Cesar QueirozHighway AdvisorWorld Bank, 1818 H
Street NWWashington DC 20433 USATel 1
202-473 8053Fax 1 202 522 3223Email
cqueiroz_at_worldbank.orghttp//www.worldbank.org/tr
ansporthttp//www.worldbank.org/highways