World Bank Experience: Road Asset Management and Development through Public-Private Partnerships Cesar Queiroz Highway Advisor World Bank Kyiv, March 21, 2006

1 / 32
About This Presentation
Title:

World Bank Experience: Road Asset Management and Development through Public-Private Partnerships Cesar Queiroz Highway Advisor World Bank Kyiv, March 21, 2006

Description:

World Bank Toolkit for PPP in Highways ... Kerf and et al. (1998). ' Concessions for Infrastructure: A Guide to Their Design and Award. ... – PowerPoint PPT presentation

Number of Views:75
Avg rating:3.0/5.0
Slides: 33
Provided by: MarciaQ2

less

Transcript and Presenter's Notes

Title: World Bank Experience: Road Asset Management and Development through Public-Private Partnerships Cesar Queiroz Highway Advisor World Bank Kyiv, March 21, 2006


1
World Bank Experience Road Asset Management and
Development through Public-Private
PartnershipsCesar QueirozHighway AdvisorWorld
BankKyiv, March 21, 2006
First International Conference Perspectives for
Ukraine on Implementation of Public-Private
Partnerships
2
Outline
  • Brief International Overview
  • Lessons Learned from Past Transport PPPs
  • How Can the World Bank Group Support PPP
    Development
  • Selection of the Strategic Investor
  • World Bank Toolkit for PPP in Highways
  • Allocation of Risks and Payment Mechanisms (e.g.,
    availability fees, shadow tolls, BOT, BOO)
  • Estimating Minimum Toll Rates to Attract Private
    Investors
  • The Way Forward

3
PPPs are becoming a global business however
reaching financial close remains a challenge
Source Public Works Financing-Major Project
Survey 1995-2004
4
PPPs remain concentrated in a select group of
countries
5
What Have We Learned?
  • Successfully concluding a transport PPP is a
    challenge
  • As a result of unrealistic and aggressive bids, a
    large number of projects face re-negotiation
  • Government commitment can disappear in periods of
    financial stress
  • Historically only 55 of proposed projects have
    reached financing

6
What Have We Learned?
  • Cost recovery is a major challenge
  • Full cost recovery is only achievable in some
    transport sub-sectors
  • Revenue projections often suffer from a bias
    towards optimism
  • The vulnerability of PPP projects to changing
    political, financial and economic circumstances
    is often underestimated
  • Access to local currency funding is a critical
    success factor for infrastructure projects with
    local currency revenues

7
Selection of the Strategic Investor or
Concessionaire
  • For large projects, it is recommended to carry
    out
  • 1. Prequalification
  • 2. A Two-Stage Bidding

8
Prequalification
  • Advertising notice requesting expressions of
    interest to pre-qualify to be published locally
    and internationally
  • Investor feedbackmeeting with selected potential
    investors/ concessionaires
  • Public informationinformation dissemination on
    the financing and construction of the project
  • Pre-qualificationinclude financial and
    operational criteria to ensure bids from only
    qualified candidates

9
Two-Stage Bidding
The First Stage
Client prepares functional performance
specifications
Bidders offer unpriced technical proposals
Client evaluates technical proposals, and
indicates what bidders should do to make their
bids responsive
The Second Stage
Client sends memorandum of changes for each
bidder and addendum to bid documents, if necessary
Bidders offer amended bids containing their final
technical proposal and a financial proposal
Client evaluates combined technical and financial
proposals
10
Unsolicited Proposals to Governments
  • Origin of most controversial private
    infrastructure projects
  • In theory, generate beneficial ideas
  • In practice, some unfavorable experiences (e.g.,
    attempt to avoid competition, exclusive
    negotiations behind closed doors)
  • Usually sole-source negotiations take much longer
    than expected

11
Should Governments Forbid Unsolicited Proposals?
  • Some governments forbid all unsolicited proposals
    to reduce public sector corruption and
    opportunistic behavior by private companies (e.g.
    Colombia)
  • Some countries require market-testing (e.g.,
    Sri Lanka, Australian States)
  • Some recognize a good project idea in the tender
    by compensating the original project proponent
    while holding an ICB (e.g., Chile, S. Africa, S.
    Korea)

12
Incentive Schemes
  • How can the government provide incentives
  • for private sector firms to participate?
  • Cost sharing and pricing arrangements
  • Incentive payments (or penalties) linked to
    performance standards
  • Support the provision of guarantees
  • (e.g., World Bank Partial Risk Guarantee)

13
World Bank Group Instruments Available to Support
PPPs
  • The World Bank
  • Loans to governments
  • Partial credit and partial risk guarantees
  • Technical assistance
  • International Finance Corporation - IFC
  • Loans to the private sector
  • Equity investment
  • Technical Assistance
  • Multilateral Investment Guarantee Agency - MIGA
  • Political risk insurance

14
Possible Roles of the World Bank
  • Financing part of government subsidies to the
    construction cost of a project
  • Providing a Partial Risk Guarantee (PRG) to the
    private investors reduced interest rate,
    increased maturity

15
World Bank Partial Risk Guarantee Structure
Governt
World Bank
Counter Guarantee
World Bank Guarantee
Concession Agreement
Project Company or Concessionaire
Private Lenders
Loan Agreement
16
PRG for a Sub-national Project
Counter Guarantee
WB Guarantee
Private Lenders
Federal Government
Buys Guarantee
Legal Framework
Loan Agreement
Provincial Government
Concession
Project SPV
17
Coverage of World Bank PRGs
  • Cover specific government obligations to a
    private project
  • Guarantee payment against default on private debt
    due to non-performance of government contractual
    obligations
  • Relevant when there is a high perceived risk of
    policy reversal
  • Coverage examples
  • performance of government or state owned
    entities, e.g., government contractual purchase
    and supply obligations
  • political events, e.g., changes in law,
    expropriation, nationalization contract
    frustration obstruction in arbitration process
    non-payment of termination amount or arbitral
    award
  • certain force majeure events
  • foreign exchange convertibility/transferability

18
Benefits of WB Partial Risk Guarantees for
  • Public sector
  • Catalyze private financing and facilitate PPP
  • Reduce government risk exposure by shifting
    commercial risk to the private sector
  • Encourage larger co-financing
  • Private sector
  • Reduce risk of private transactions
  • Mitigate risks difficult for the private sector
    to manage
  • Open new markets
  • Lower the cost of financing and extend maturities
  • Improve project sustainability

19
Partial Risk Guarantee Facility for Perus
Infrastructure PPP Program
  • Facility Size US 200 million Maximum
    individual guarantee amount US 50 million
  • Project Eligibility Criteria
  • Projects in the infrastructure sector
  • PPP concession (or similar) contracts
  • Economically and socially desirable and
    technically viable, but financially viable only
    with appropriate government support
  • In compliance with applicable WB safeguard
  • Coverage Up to 50 of project debt against
    political, regulatory and breach of contract
    risks to project lenders
  • Duration 5 years of government obligations on a
    rolling basis for a maximum of 15 years
  • Currency Local currency or US denominated debt

20
Basic Assumptions to Estimate the Minimum Toll
Rate to Attract Private Investors for a PPP
Project
  • Concession term 20 yrs
  • Construction Cost 1M/km to 5M/km
  • Operation cost 500,000/km/yr
  • Equity 14
  • Subsidies 0
  • Interest rate 5/yr
  • Grace period 4 yrs
  • Repayment period 14 years
  • Discount rate 10
  • Initial traffic 5,000 vpd to 20,000 vpd
  • Traffic growth 3
  • Inflation 6
  • Tax 18
  • IRR 12
  • ROE 16
  • LLCR 1.0
  • DSCR 1.0

21
Toolkit for PPP in Highways
  • The toolkit is structured under five headings and
    includes a library and interactive financial
    simulation model

Available on the World Bank web site
www.worldbank.org/highways
22
(No Transcript)
23
Estimated Minimum Toll Rate to Attract Private
Investment for a PPP Project
/km
5,000 vpd
10,000 vpd
15,000 vpd
20,000 vpd
Construction cost, million/km
24
Value Engineering
  • A professionally applied, function oriented,
    creative and systematic team management approach,
    used to analyze and improve value in
    transportation projects
  • Provides a balance of quality, performance and
    functionality in a project, minimizing life cycle
    costs of construction, operation and maintenance

25
Benefits of Public Disclosure of Concession
Agreements
  • Further check on corruption, which in addition to
    its direct benefits can enhance the legitimacy of
    private sector involvement in often sensitive
    sectors
  • Provision of consumers with a clearer sense of
    their rights and obligations, and can facilitate
    public monitoring of concessionaire performance

26
Payment Mechanisms
  • Availability Fee is paid to the concessionaire by
    the government based on the availability of
    required capacity (number of lanes in
    satisfactory condition)
  • Shadow Toll is paid to the concessionaire by the
    government, not charged to motorists, on the
    basis of veh-km achieved (volume and composition
    of traffic)
  • BOT is a scheme where the government contributes
    land to the project and sometimes a negotiated
    financial support, while the concessionaire
    builds, maintains and operates the motorway and
    transfer the assets after the concession
    completion. The commercial risk rests with the
    concessionaire
  • BOO is similar to BOT, but does not involve the
    transfer of the assets to the government

27
Allocation of Risks by Forms of Concession
100
Availability Fee
Shadow Tolls
RISK TO PUBLIC SECTOR
BOT
BOO
Decreasing Public Risks, Increasing Private Risks
0
100
RISK TO PRIVATE SECTOR
28
Transport Infrastructure Way Forward in Ukraine
  • Developing local currency markets for
    contributing to transport infrastructure
    development
  • Learning from lessons of experience from regional
    transition economies, e.g., motorways in Hungary,
    ports in Poland
  • Structuring PPPs is a complex, time demanding
    exercise that requires dedicated resources from
    the public sector consider establishing a
    Transport PPP Unit
  • Selecting a small number of transactions with the
    highest potential for success in the short term
  • Developing a consistent and organized approach to
    assess, evaluate and monitor contingent
    liabilities arising from public financial support
    to PPP transport projects
  • Developing smart and effective risk mitigation
    products for supporting PPPs

29
(No Transcript)
30
Thank you!
31
Some Basic References
  • World Bank (2001). World Bank-Financed
    Procurement Manual Draft. Washington, D.C.
    http//siteresources.worldbank.org/PROCUREMENT/Res
    ources/pm7-3-01.pdf
  • Guasch, J. Luis (2004). Granting and
    Renegotiating Infrastructure Concessions Doing It
    Right. Washington, D.C. World Bank.http//www-wd
    s.worldbank.org/servlet/WDSContentServer/WDSP/IB/2
    004/05/06/000090341_20040506150118/Rendered/PDF/28
    8160PAPER0Granting010renegotiating.pdf
  • World Bank (2004). Guidelines Procurement
    Under IBRD Loans and IDA Credits. (May).
    Washington, D.C. http//siteresources.worldbank.or
    g/INTPROCUREMENT/Resources/Procurement-May-2004.pd
    f
  • Queiroz, Cesar (2005). Launching Public Private
    Partnerships for Highways in Transition
    Economies. Transport Paper TP-9. (September).
    Washington, D.C. World Bank.
  • Kerf and et al. (1998). Concessions for
    Infrastructure A Guide to Their Design and
    Award. Technical Paper no. 389.
  • World Bank (1998). Bidding for Private
    Concessions. The Use of World Bank Guarantees.
    RMC Discussion Paper Series, no 120. Washington,
    D.C.

32
Cesar QueirozHighway AdvisorWorld Bank, 1818 H
Street NWWashington DC 20433 USATel 1
202-473 8053Fax 1 202 522 3223Email
cqueiroz_at_worldbank.orghttp//www.worldbank.org/tr
ansporthttp//www.worldbank.org/highways
Write a Comment
User Comments (0)